9 total
Negligence Case allowed
This decision addresses prejudgment and postjudgment interest and trial costs following a bifurcated damages trial.
The court determined that the plaintiffs' damages award of $1,083,713.26 for diminution in value and lost rental income should be reduced by $436,892.13 in insurance monies received, resulting in a net damage award of $658,054.28.
Tega's Rule 49 offer to settle for $650,000 plus prejudgment interest (totaling $693,754.79) was found to be more favourable than the plaintiffs' net recovery.
Consequently, the plaintiffs were awarded partial indemnity costs up to the date of Tega's offer (December 29, 2015), and Tega was awarded partial indemnity costs from that date forward.
The court also disallowed expert fees for one of the plaintiffs' experts whose evidence was deemed unhelpful.
Motion to strike largely dismissed; negligence claims struck but amendment allowed.
The defendant brought a motion to strike the plaintiff’s statement of claim without leave to amend under Rules 21.01 and 25.11 of the Rules of Civil Procedure, arguing the pleading disclosed no reasonable cause of action and constituted an abuse of process.
The defendant alternatively sought further and better particulars of alleged construction delays and related claims.
The court held the statement of claim disclosed a viable cause of action in breach of contract and was not frivolous or vexatious.
Although portions pleading negligence were struck due to contractual limitations restricting claims to breach of contract, the plaintiff was granted leave to amend.
The court also dismissed the request for particulars, finding the information sought was largely within the defendant’s knowledge and amounted to improper attempts to obtain evidence prior to discovery.
Appeal dismissed; Ontario court lacked jurisdiction over federal construction contract claim arising in Quebec.
The appellant, a successful bidder on a federal dam construction contract in Quebec, sued the federal Crown in Ontario for negligent misstatement and breach of contract.
The motion judge struck the action for lack of subject-matter jurisdiction under s. 21(1) of the Crown Liability and Proceedings Act, finding the contract claim arose in Quebec and the tort claim was extinguished by the contract's general conditions.
The Court of Appeal upheld the decision, confirming the motion judge applied the correct test to determine where the substance of the claim arose and correctly interpreted the contract as providing an exclusive mechanism for resolving claims.
Contract barred tort claims; remaining claim arose in Quebec, defeating Ontario jurisdiction.
The federal Crown brought a motion to strike an action for breach of contract and negligent misrepresentation relating to a construction contract for the replacement of a dam in Quebec.
The court held that the contractual claim arose in Quebec because the project, contract administration, and relevant decisions occurred there.
Although the alleged negligent misrepresentation claim was connected to Ontario because tender documents were obtained and relied upon in Ontario, the contract constituted a complete code governing compensation for extra costs and delays.
Interpreting the contract, the court concluded that the parties had excluded concurrent liability in tort.
As a result, the negligent misrepresentation claim was struck and the remaining contractual claim, which arose in Quebec, could not be heard in Ontario under the Crown Liability and Proceedings Act.
Non-parties denied costs after being briefly joined in summary judgment motion.
Two non-parties sought costs following a summary judgment motion brought by the defendant seeking dismissal of part of the plaintiff’s claim relating to subcontractors.
The defendant had initially served the non-parties but abandoned the motion as against them shortly before the hearing.
The non-parties argued they incurred preparation costs due to the defendant’s tactical decision to include them.
The court held that it was not inappropriate for the defendant to join the non-parties at the time and noted that the non-parties did not file responding materials or participate in the motion.
In the circumstances, the court declined to award costs against the defendant.
General contractor may advance subcontractor delay claims against owner through prime contract.
The defendant Crown brought a motion for partial summary judgment seeking dismissal of claims advanced by a general contractor on behalf of subcontractors arising from delays in a federal construction project.
The Crown argued that the subcontractors lacked privity of contract with the owner, that the contractor had not itself suffered damages, and that the claims were barred by limitation periods and lack of contractual notice.
The court held that the contractual scheme contemplated subcontracting and permitted the contractor to pursue delay damages that included sums payable to subcontractors where liability rested with the owner.
The absence of direct contractual privity between subcontractors and the owner was not a bar where the contractor’s contract allowed recovery of such costs and the subcontract conditioned payment on recovery from the owner.
The court concluded that the subcontractor claims raised a reasonable cause of action and that genuine issues required a trial.
Campground owners ordered to pay $15,225 and retrofit facilities for failing to accommodate mobility disability.
The applicant, who has a degenerative disease limiting his mobility, filed a human rights application alleging the respondents failed to accommodate his disability at their campground.
The applicant rented a trailer site and required a mobility scooter, but could not access the campground store, public telephone, garbage bins, or community washrooms.
The Tribunal found that the respondents breached the Human Rights Code by failing to make the public facilities accessible to the point of undue hardship.
The Tribunal awarded the applicant $15,225 in monetary compensation for loss of enjoyment and injury to dignity, feelings, and self-respect, plus pre-judgment interest.
The Tribunal also ordered the corporate respondent to provide accessible washrooms and ensure the store ramp met building code requirements.
Appeal dismissed; stopping payment on a certified cheque and demanding an unjustified bond constituted fundamental breach.
The appellants, Axor Construction Canada Inc. and London Guarantee Insurance Company, appealed a trial judgment awarding the respondent $455,462.85 in damages under the Construction Lien Act.
The dispute arose from a construction subcontract where the appellant stopped payment on a certified cheque due to a backcharge related to a Fair Wage Policy.
The Divisional Court upheld the trial judge's finding that the appellant's actions, including stopping payment and demanding an unjustified bond, constituted a fundamental breach of contract that excused the respondent from continued performance.
The appeals were dismissed with costs.
Appeal dismissed; delivery of a performance bond to the owner is required for it to be effective.
The appellants appealed a decision regarding the effectiveness of a performance bond that was signed by the contractor and the bond company but never delivered to the owner.
The Supreme Court of Canada dismissed the appeal, adopting the reasons of the Court of Appeal for Ontario, which held that delivery is required to make the bond effective.