This decision determines the costs of a successful motion brought by the defendant, 485 Logan Developments Inc., to declare the plaintiff's construction lien expired.
The court found that the plaintiff had engaged in 'bootstrapping' by performing minor work solely to fabricate a new lien period after the original had expired.
Under section 86(1) of the Construction Act, such abusive conduct justified an award of substantial indemnity costs.
Consequently, the court ordered the plaintiff to pay the defendant $45,000 in substantial indemnity costs within 45 days.