Tribunal scheduled a 13-day hearing and issued a procedural order for an expropriation compensation claim.
The Ontario Land Tribunal held a Case Management Conference regarding a claim for compensation arising from the expropriation of property by Metrolinx.
The Tribunal scheduled a 13-day video hearing to commence in October 2024 and issued a Procedural Order to govern the proceeding.
Motion for production of partial settlement details denied; settlement amount and negotiation documents protected by privilege.
The plaintiff subcontractor brought a motion to compel the defendant general contractor to produce documents relating to a partial settlement reached between the general contractor and the defendant owner.
The court reviewed the law on Pierringer agreements and settlement privilege, concluding that the quantum of the settlement and the negotiation documents were protected by settlement privilege and did not need to be produced to the non-settling plaintiff at this stage of the litigation.
The motion for production was dismissed.