The plaintiff, a general contractor, commenced an action against the defendant mechanical subcontractor regarding a construction project.
The defendant had previously commenced a construction lien action which was referred to a Master for trial.
The plaintiff brought a motion on consent to refer this action to the same Master to be tried with or immediately following the lien action, to avoid multiplicity of proceedings and inconsistent findings.
The court granted the consent order.