Following a construction lien trial in which the plaintiff recovered the balance owing for stone installation and successfully defended a counterclaim alleging deficiencies, the court determined the appropriate costs award.
The plaintiff sought full or substantial indemnity costs, arguing that the defendants engaged in unreasonable conduct by presenting inflated invoices contradicted by their own witness and by making misleading testimony.
The court held that the conduct was unreasonable but did not rise to the level warranting full or substantial indemnity costs.
Considering the factors under Rule 57 of the Rules of Civil Procedure, the parties’ settlement offers, the complexity of the construction litigation, and proportionality, the court awarded costs slightly above partial indemnity.
Costs were fixed at $50,000 plus HST and $3,000 in disbursements.