The plaintiff, a contractor, sued the defendant homeowner for unpaid contracting fees of $35,729.63 for building a log home.
The defendant counterclaimed against the contractor and the log home kit supplier for $124,203.30, alleging breach of contract due to delays and construction deficiencies.
The court found that the defendant homeowner, who acted as his own general contractor, was responsible for the delays and had wrongfully repudiated the contract by locking the contractor out of the site.
The court granted the plaintiff's claim for the unpaid balance and dismissed the defendant's counterclaim.