The moving parties, professional engineers and engineering firms involved in the design and construction of the Nipigon River Bridge, brought a motion to stay disciplinary proceedings against them on the basis of delay.
The Discipline Committee found that the Association of Professional Engineers of Ontario (PEO) was responsible for approximately 36 months of inordinate delay in its investigation.
However, the Committee dismissed the motion, concluding that the moving parties failed to establish significant prejudice that would compromise hearing fairness or amount to an abuse of process.
The Committee further held that the public interest in holding a hearing on the merits regarding the failure of major public infrastructure outweighed any disrepute caused by the delay.