Expropriation claims by owner and tenant consolidated and scheduled for phased hearing.
A case management conference was held regarding two expropriation claims against Metrolinx by a property owner and its tenant.
The Tribunal ordered the consolidation of the two proceedings on consent.
The Tribunal rejected Metrolinx's request to delay the hearing pending the outcome of unrelated planning appeals, finding no justifiable basis for delay.
A 13-day first phase hearing was scheduled for February 2024 to determine market value and injurious affection, with a second phase deferred to address disturbance damages and further injurious affection once the infrastructure work is completed.
OLTOntario Land TribunalApr 11, 2023