The defendant general contractor brought a motion to dismiss the plaintiff subcontractor's action, obtain default judgment on its counterclaim, and cancel a lien bond.
The plaintiff had abandoned the action after its counsel was removed from the record.
Another subcontractor opposed the cancellation of the lien bond, arguing it should be pooled to cover its own costs and interest.
The court dismissed the plaintiff's action, granted default judgment on the counterclaim, and ordered the lien bond cancelled, finding that the pooling provisions of the Construction Lien Act did not apply where all liens had been bonded off.