C.M. Callow Inc. v. Zollinger
Supreme Court of Canada | 2020 SCC 45 | December 18, 2020
Coram: Wagner C.J. and Abella, Moldaver, Karakatsanis, Côté, Brown, Rowe, Martin and Kasirer JJ.
Reasons for Judgment (paras. 1 to 120): Kasirer J. (Wagner C.J. and Abella, Karakatsanis and Martin JJ. concurring)
Concurring Reasons (paras. 121 to 182): Brown J. (Moldaver and Rowe JJ. concurring)
Dissenting Reasons (paras. 183 to 238): Côté J.
Headnote
Contracts — Breach — Performance — Duty of honest performance — Clause in winter maintenance agreement permitting unilateral termination of contract without cause upon 10 days' notice — Contract terminated by condominium corporations with required notice to contractor — Contractor suing for breach of contract — Trial judge finding that statements and conduct by condominium corporations actively deceived contractor and led it to believe contract would not be terminated — Trial judge awarding damages for breach of contract — Whether exercise of termination clause constituted breach of duty of honest performance.
In 2012, a group of condominium corporations ("Baycrest") entered into a two‑year winter maintenance contract and into a separate summer maintenance contract with C.M. Callow Inc. ("Callow"). Pursuant to clause 9 of the winter maintenance contract, Baycrest was entitled to terminate that agreement if Callow failed to give satisfactory service in accordance with its terms. Clause 9 also provided that if, for any other reason, Callow's services were no longer required, Baycrest could terminate the contract upon giving 10 days' written notice.
In early 2013, Baycrest decided to terminate the winter maintenance agreement but chose not to inform Callow of its decision at that time. Throughout the spring and summer of 2013, Callow had discussions with Baycrest regarding a renewal of the winter maintenance agreement. Following those discussions, Callow thought that it was likely to get a two‑year renewal of the winter maintenance contract and that Baycrest was satisfied with its services. During the summer of 2013, Callow performed work above and beyond the summer maintenance contract at no charge, which it hoped would act as an incentive for Baycrest to renew the winter maintenance agreement.
Baycrest informed Callow of its decision to terminate the winter maintenance agreement in September 2013. Callow filed a statement of claim for breach of contract, alleging that Baycrest acted in bad faith. The trial judge held that the organizing principle of good faith performance and the duty of honest performance were engaged. She was satisfied that Baycrest actively deceived Callow from the time the termination decision was made to September 2013, and found that Baycrest acted in bad faith by withholding that information to ensure Callow performed the summer maintenance contract and by continuing to represent that the contract was not in danger despite knowing that Callow was taking on extra tasks to bolster the chances of the winter maintenance contract being renewed. She awarded damages to Callow in order to place it in the same position as if the breach had not occurred. The Court of Appeal set aside the judgment at first instance, holding that the trial judge erred by improperly expanding the duty of honest performance beyond the terms of the winter maintenance agreement. Further, it held that any deception in the communications during the summer of 2013 related to a new contract not yet in existence, namely the renewal that Callow hoped to negotiate, and therefore was not directly linked to the performance of the winter contract.
Held (Côté J. dissenting): The appeal should be allowed and the judgment of the trial judge reinstated.
Per Wagner C.J. and Abella, Karakatsanis, Martin and Kasirer JJ.: The duty to act honestly in the performance of the contract precluded the active deception by Baycrest by which it knowingly misled Callow into believing that the winter maintenance agreement would not be terminated. By exercising the termination clause dishonestly, it breached the duty of honesty on a matter directly linked to the performance of the contract, even if the 10‑day notice period was satisfied. Accordingly, the Court of Appeal should not have interfered with the conclusions of the trial judge.
The duty of honest performance in contract, formulated in Bhasin v. Hrynew, 2014 SCC 71, [2014] 3 S.C.R. 494, applies to all contracts and requires that parties must not lie or otherwise knowingly mislead each other about matters directly linked to the performance of the contract. In determining whether dishonesty is connected to a given contract, the relevant question is whether a right under that contract was exercised, or an obligation under that contract was performed, dishonestly. While the duty of honest performance is not to be equated with a positive obligation of disclosure, in circumstances where a contracting party lies to or knowingly misleads another, a lack of a positive obligation of disclosure does not preclude an obligation to correct a false impression created through that party's own actions.
The organizing principle of good faith recognized in Bhasin is not a free‑standing rule, but instead manifests itself through existing good faith doctrines. While the duty of honest performance and the duty to exercise discretionary powers in good faith are distinct, like each of the different manifestations of the organizing principle, they should not be thought of as disconnected from one another. The duty of honest performance shares a common methodology with the duty to exercise contractual discretionary powers in good faith by fixing on the wrongful exercise of a contractual prerogative. Each of the specific legal doctrines derived from the organizing principle rest on a requirement of justice that a contracting party have appropriate regard to the legitimate contractual interests of their counterparty. They need not subvert their own interests to those of the counterparty by acting as a fiduciary or in a selfless manner. This requirement of justice reflects the notion that the bargain, the rights and obligations agreed to, is the first source of fairness between parties to a contract. Those rights and obligations must be exercised and performed honestly and reasonably and not capriciously or arbitrarily where recognized by law.
The duty of honesty as contractual doctrine has a limiting function on the exercise of an otherwise complete and clear right since the duty, irrespective of the intention of the parties, applies to the performance of all contracts, and by extension, to all contractual obligations and rights. Instead of constraining the decision to terminate in and of itself, the duty of honest performance attracts damages where the manner in which the right was exercised was dishonest. This focus on the manner in which the termination right was exercised should not be confused with whether the right could be exercised. No contractual right, including a termination right, can be exercised dishonestly and, as such, contrary to the requirements of good faith.
The requirements of honesty in performance can go further than prohibiting outright lies. Whether or not a party has knowingly misled its counterparty is a highly fact‑specific determination, and can include lies, half‑truths, omissions, and even silence, depending on the circumstances. One can mislead through action, by saying something directly to its counterparty, or through inaction, by failing to correct a misapprehension caused by one's own misleading conduct.
The duty of honest performance is a contract law doctrine, not a tort and therefore a nexus with the contractual relationship is required. A breach must be directly linked to the performance of the contract. The framework for abuse of rights in Quebec is useful to illustrate the required direct link between dishonesty and performance from Bhasin. Authorities from Quebec serve as persuasive authority and comparison between the common law and civil law as they evolve in Canada is a particularly useful and familiar exercise for the Court. Like in the Quebec civil law, no contractual right may be exercised dishonestly and therefore contrary to the requirements of good faith. The direct link exists when the party performs their obligation or exercises their right under the contract dishonestly. While the duty of honest performance has similarities with civil fraud and estoppel, it is not subsumed by them. Unlike estoppel and civil fraud, the duty of honest performance does not require a defendant to intend that the plaintiff rely on their representation or false statement.
The duty of honest performance attracts damages according to the ordinary contractual measure. The ordinary approach is to award contractual damages corresponding to the expectation interest. That is, damages should put the injured party in the position that it would have been in had the duty been performed. Although reliance damages, which are the ordinary measure of damages in tort, and expectation damages will be the same in many if not most cases, they are conceptually distinct, and there is no basis to hold that a breach of the duty of honest performance should in general be compensated by way of reliance damages.
In the instant case, Baycrest knowingly misled Callow in the manner in which it exercised clause 9 of the winter maintenance agreement and this wrongful exercise of the termination clause amounts to a breach of contract. Even though Baycrest had what was, on its face, an unfettered right to terminate the winter maintenance agreement on 10 days' notice, the right had to be exercised in keeping with the duty to act honestly. Baycrest's deception was directly linked to this contract, because its exercise of the termination clause was dishonest. It may not have had a free‑standing obligation to disclose its intention to terminate, but it nonetheless had an obligation to refrain from misleading Callow in the exercise of that clause. Baycrest had to refrain from false representations in anticipation of the notice period. If someone is led to believe that their counterparty is content with their work and their ongoing contract is likely to be renewed, it is reasonable for that person to infer that the ongoing contract is in good standing and will not be terminated early. Having failed to correct Callow's misapprehension that arose due to these false representations, Baycrest breached its duty of good faith in the exercise of its right of termination. Damages thus flow for the consequential loss of opportunity. While damages are to be measured against a defendant's least onerous means of performance, the least onerous means of performance in this case would have been to correct the misrepresentation once Baycrest knew Callow had drawn a false inference. Had it done so, Callow would have had the opportunity to secure another contract for the upcoming winter.
Per Moldaver, Brown and Rowe JJ.: As a universally applicable minimum standard, all contracts must be performed honestly. Contracting parties may therefore not lie to, or otherwise knowingly mislead, each other about matters directly linked to performance. If a plaintiff suffers loss in reliance on its counterparty's misleading conduct, the duty of honest performance serves to make the plaintiff whole. It does not, however, impose a duty of loyalty or of disclosure or require a party to forego advantages flowing from the contract. The dividing line between (1) actively misleading conduct, and (2) permissible non‑disclosure has been clearly demarcated by cases addressing misrepresentation and the same settled principles apply to the duty of honest performance, although it also applies (unlike misrepresentation) to representations made after contract formation.
There is, in the context of misrepresentation, a rich law accepting that sometimes silence or half‑truths amount to a statement. Although contracting parties have no duty to disclose material information, a contracting party may not create a misleading picture about its contractual performance by relying on half‑truths or partial disclosure. Representations need not take the form of an express statement. So long as it is clearly communicated, it may comprise other acts or conduct on the part of the defendant. The entire context, which includes the nature of the parties' relationship, is to be considered in determining, objectively, whether the defendant made a representation to the plaintiff. The question is whether the defendant's active conduct contributed to a misapprehension that could be corrected only by disclosing additional information. Contracting parties are required to correct representations that are subsequently rendered false, or which the representor later discovers were erroneous. The question of whether a representation has been made is a question of mixed fact and law, subject to appellate review only for palpable and overriding error.
The legal aim in remedying a breach of contract is to give the innocent party the full benefit of the bargain by placing it in the position it would have occupied had the contract been performed. But the justification for awarding expectation damages does not apply to breach of the duty of honest performance. In such cases, the issue is not that the defendant has failed to perform the contract, thereby defeating the plaintiff's expectations. It is, rather, that the defendant has performed the contract, but has also caused the plaintiff loss by making dishonest extra‑contractual misrepresentations concerning that performance, upon which the plaintiff relied to its detriment. The plaintiff's complaint is not lost value of performance, but detrimental reliance on dishonest misrepresentations. The interest being protected is not an expectation interest, but a reliance interest. And just as these are unrelated interests, an expectation measure of damage is unrelated to the breach of the duty of honest performance.
Much like estoppel and civil fraud, the duty of honest performance vindicates the plaintiff's reliance interest. A contracting party that breaches this duty will be liable to compensate its counterparty for any foreseeable losses suffered in reliance on the misleading representations. The duty of honest performance is not subsumed by estoppel and civil fraud; rather, it protects the reliance interest in a distinct and broader manner since the defendant may be held liable even where it does not intend for the plaintiff to rely on the misleading representation. Irrespective of the defendant's intention, all a plaintiff need show is that, but for its reliance on the misleading representation, it would not have sustained the loss.
Disposing of the present case is a simple matter of applying the Court's decision in Bhasin; Callow's claim should be resolved by applying only the duty of honest performance. There is no basis for disturbing the trial judge's conclusions. Baycrest's conduct did not fall on the side of innocent non‑disclosure. The trial judge found that active communications between the parties deceived Callow. Baycrest identifies no palpable and overriding error to justify overturning these conclusions. The proper measure of damages represents the loss Callow suffered in reliance on Baycrest's misleading representations.
The majority relies on the civilian concept of "abuse of rights" in its analysis. In so doing, it departs from the Court's accepted practice in respect of comparative legal analysis. The principles that apply to this appeal are determinative and settled. Canada's common law and civil law systems have adopted very different approaches to the place of good faith in contract law. The majority's reliance on the civilian doctrine of abuse of a right distorts the analysis in Bhasin and elides the distinction between honest performance and good faith in the exercise of a contractual discretion.
Courts should draw on external legal concepts only where domestic law does not provide an answer or where it is necessary to modify or otherwise develop an existing legal rule. Courts may also look to the experience of other legal systems in considering whether a potential solution to a legal problem will result in negative consequences, or to observe that a domestic legal concept mirrors one found in another system. Even where comparative analysis is appropriate, it must be undertaken with care and circumspection. The golden rule in using concepts from one of Canada's legal systems to modify the other is that the proposed solution must be able to completely and coherently integrate into the adopting system's structure.
Per Côté J. (dissenting): The appeal should be dismissed. Callow's recourse cannot be based on a breach of the duty of honest performance. Although Baycrest's conduct may not be laudable, it does not fall within the category of active dishonesty prohibited by that duty.
The duty of honest performance is described in Bhasin as a simple requirement not to lie or knowingly mislead about matters directly linked to performance of the contract. The requirement that parties not lie is straightforward; however, the kind of conduct covered by the requirement that they not otherwise knowingly mislead each other is not. The law imposes neither a duty of loyalty or of disclosure nor a requirement to forego advantages flowing from the contract on a contracting party. Absent a duty to disclose, it is far from obvious when exactly one's silence will knowingly mislead the other contracting party or at what point a permissible silence turns into a non‑permissible silence that may constitute a breach of contract. In any event, the duty of honest performance should remain clear and easy to apply.
The obligations flowing from the duty of honest performance are negative obligations. Extending the duty beyond that scope would detract from certainty in commercial dealings. Therefore, silence cannot be considered dishonest within the meaning of Bhasin unless there is a positive obligation to speak. Such an obligation does not arise simply because a party to a contract realizes that his counterparty is operating under a mistaken belief. Absent a duty of disclosure, a party to a contract has no obligation to correct his counterparty's mistaken belief unless the party's active conduct has materially contributed to it. What constitutes a material contribution will obviously depend upon the context, which includes the nature of the parties' relationship as well as the relevant provisions of the contract. Parties that prefer not to disclose certain information — which they are entitled not to do — are not required to adopt a new line of conduct in their contractual relationship simply because they chose silence over speech.
In the context of a right to terminate a contract without cause, a party that intends to end an agreement does not have to convey hints in order to alert his counterparty that their business relationship is in danger. No obligation to speak arises when a party becomes aware of his counterparty's mistaken belief that the contract will not be terminated unless the party has taken positive action that materially contributed to that belief. If one party leads another to believe that their contract will be renewed, it follows that the other party can reasonably expect their business relationship to be extended rather than terminated. But an inference to that effect cannot be drawn in the abstract. In order to infer that one party, through discussions about renewal, led the other party to think that there was no risk their existing agreement would be terminated, the inference‑drawing process must obviously take into account the nature of the risk at stake and what was actually communicated during those discussions. Otherwise, the inference would entail a palpable and overriding error that would be subject to appellate review.
In the present case, Baycrest bargained for a right to terminate its winter agreement for any reason and at any time upon giving 10 days' notice. In her assessment of Baycrest's conduct, the trial judge did not ask herself if Baycrest lied or otherwise knowingly misled Callow about the exercise of its right to terminate the winter agreement for any other reason than unsatisfactory services. She wrongfully insisted on addressing alleged performance issues despite the fact that the winter agreement could be terminated even if Callow's services were satisfactory. The trial judge also did not consider that the active deception had to be directly linked to the performance of the contract. It is clear that the representations she found had been made by Baycrest were not directly linked to the performance of the winter agreement. The trial judge's misunderstanding of the applicable legal principles vitiated the fact‑finding process.
Reasons for Judgment
I. Introduction
[ 1 ] This appeal concerns a clause in a commercial winter maintenance agreement that permitted the clients to terminate the contract unilaterally, without cause, upon giving the contractor 10 days' notice. The dispute does not turn on whether the clause represented a fair bargain between the parties. There is also no issue about the meaning of the termination clause. The dispute turns rather on the manner in which the respondents (collectively "Baycrest") exercised the termination clause. Acknowledging that 10 days' notice was given the appellant, C.M. Callow Inc. ("Callow"), argues that Baycrest exercised the termination clause contrary to the requirements of good faith set forth by this Court in Bhasin v. Hrynew, 2014 SCC 71, [2014] 3 S.C.R. 494, in particular the duty to perform the contract honestly.
[ 2 ] In Bhasin, Cromwell J. recognized a general organizing principle of good faith, which means that "parties generally must perform their contractual duties honestly and reasonably and not capriciously or arbitrarily" (para. 63). This organizing principle, he explained, "is not a free-standing rule, but rather a standard that underpins and is manifested in more specific legal doctrines and may be given different weight in different situations" (para. 64). The organizing principle of good faith manifests itself through "existing doctrines" addressing "the types of situations and relationships in which the law requires, in certain respects, honest, candid, forthright or reasonable contractual performance" (para. 66).
[ 3 ] In this appeal, the applicable good faith doctrine is the duty of honesty in contractual performance. As Cromwell J. explained in Bhasin, at para. 73, the duty of honesty applies to all contracts as a matter of contractual doctrine, and means "simply that parties must not lie or otherwise knowingly mislead each other about matters directly linked to the performance of the contract". Callow says Baycrest's failure to exercise its right to terminate in keeping with the mandatory duty of honest performance amounted to a breach of contract. It points to the trial judge's findings that Baycrest withheld the information that the contract was in danger of termination. Baycrest then continued to represent that the contract was not in danger and knowingly declined to correct the false impression it had created and under which Callow was operating. This dishonesty continued for several months, "in anticipation of the notice period" wrote the trial judge and, claims Callow, resulted in it foregoing the opportunity to bid on other winter contracts and thereby justifies an award of damages (2017 ONSC 7095, at para. 67).
[ 4 ] Baycrest, for its part, recalling that Cromwell J. explicitly stated in Bhasin that the duty of honest performance does not amount to a duty to disclose, argues that its silence did not constitute dishonesty. It also says the alleged dishonesty was not connected to the contract in place at the time because, in its submission, the impugned communications related to the possibility of a future contract not yet executed. The Court of Appeal agreed and overturned the trial judge's decision (2018 ONCA 896, 429 D.L.R. (4th) 704).
[ 5 ] I respectfully disagree with the Court of Appeal on whether the manner in which the termination clause was exercised ran afoul of the minimum standard of honesty. The duty to act honestly in the performance of the contract precludes active deception. Baycrest breached its duty by knowingly misleading Callow into believing the winter maintenance agreement would not be terminated. By exercising the termination clause dishonestly, it breached the duty of honesty on a matter directly linked to the performance of the contract, even if the 10-day notice period was satisfied and irrespective of their motive for termination. For the reasons that follow, I would allow the appeal and restore the judgment of the Ontario Superior Court of Justice.
II. Background
[ 6 ] Baycrest includes 10 condominium corporations managed by Condominium Management Group and a designated property manager. Each corporation has its own board of directors to manage its affairs and, collectively, they established a Joint Use Committee ("JUC"). The JUC makes decisions regarding the joint and shared assets of the condominiums. In 2010, the condominium corporations entered into a two-year winter maintenance agreement with Callow, a corporation owned and operated by Christopher Callow. Pursuant to the terms of the agreement, Callow provided winter services, including snow removal, to the condominium corporations.
[ 7 ] At the conclusion of the two-year term in 2012, the corporations entered into two new agreements with Callow. Joseph Peixoto — president of one of the condominium corporations, and representative on the JUC — negotiated the main pricing terms with Mr. Callow for the renewal of the winter maintenance contract, which also added a separate summer maintenance services contract.
[ 8 ] At issue in this appeal is the winter maintenance agreement, which had a new two-winter term from November 1, 2012 to April 30, 2014. Pursuant to clause 9, the corporations were entitled to terminate the winter maintenance agreement if Callow failed to give satisfactory service in accordance with the terms of this Agreement. Moreover, clause 9 provided that "if for any other reason [Callow's] services are no longer required for the whole or part of the property covered by this Agreement, then the [condominium corporations] may terminate this contract upon giving ten (10) days' notice in writing to [Callow]" (A.R., vol. III, at p. 10).
[ 9 ] During the first winter of the two-winter term, there were complaints from occupants of various condominiums, many of which related to snow removal from individual parking stalls. In January 2013, Mr. Callow attended a JUC meeting to address the concerns. The minutes reflected the positive nature of this meeting, recording that "[t]he Committee confirmed that [Callow] has been diligent in addressing this issue as best as could be expected considering the nature of the storms recently experienced" (A.R., vol. III, at p. 35). After the meeting, the property manager at the time also sent a follow-up email to the JUC members: "I know that your Board has been generally satisfied with the snow removal — so there is nothing outstanding to report here" (p. 39).
[ 10 ] A few months later — still in the first year of the agreement — respondent Tammy Zollinger became the property manager. About three weeks after Ms. Zollinger's arrival, another JUC meeting was held, this time without Mr. Callow present. During the meeting, Ms. Zollinger advised the JUC to terminate the winter maintenance agreement with Callow "due to poor workmanship in the 2012-13 winter" (A.R., vol. III, at p. 43). The minutes went on to indicate that Ms. Zollinger had reviewed the contract and advised the JUC members that they could terminate the contract with Callow with no financial penalty. Ms. Zollinger further advised that she would get quotes from other snow removal contractors. The JUC voted to terminate the winter maintenance agreement shortly thereafter, "in either March or April" of 2013 (trial reasons, at para. 51). Baycrest chose not to inform Mr. Callow of its decision to terminate the winter maintenance agreement at that time.
[ 11 ] Although only one winter of the two-winter term had been completed, Callow began discussions throughout the spring and summer of 2013 with Baycrest regarding a renewal of the winter maintenance agreement. Specifically, Mr. Callow had various exchanges with two condominium corporations' board members, one of whom was Mr. Peixoto. Following these conversations, wrote the trial judge, "Mr. Callow thought that he was likely to get a two-year renewal of his winter maintenance services contract and they were satisfied with his services" (para. 41).
[ 12 ] Meanwhile, Callow continued to fulfill its obligations under the winter and summer maintenance agreements including, pursuant to the latter arrangement, finishing "spring cleanup", cutting grass on a weekly basis and conducting garbage pick-up. Furthermore, during the summer of 2013, Callow "performed work above and beyond [its] summer maintenance services contract" (para. 42), even doing what Mr. Callow described as some "freebie" work, which he hoped would act as an incentive for Baycrest to renew the winter maintenance agreement at the end of the upcoming winter.
[ 13 ] Conversations between Callow and Mr. Peixoto continued into July 2013, at which time Callow decided to improve the appearance of two gardens. In an email dated July 17, 2013, Mr. Peixoto wrote to another condominium corporation board member regarding this "freebie" work, writing in part: "It's nice he's doing it but I am sure it's an attempt at us keeping him. Btw, I was talking to him last week as well and he is under the impression we're keeping him for winter again. I didn't say a word to him cuz I don't wanna get involved but I did tell [Ms. Zollinger] that [Mr. Callow] thinks we're keeping him for winter" (A.R., vol. III, at p. 73).
[ 14 ] Baycrest did not inform Callow about the decision to terminate the winter maintenance agreement until September 12, 2013. At that point, Ms. Zollinger advised Callow by way of email "that Baycrest will not be requiring your services for the winter contract for the 2013/2014 season, as per section 9 of the contract, Baycrest needs to provide the contractor with 10 days' notice" (A.R., vol. III, at p. 49).
[ 15 ] Callow consequently filed a statement of claim for breach of contract, alleging that Baycrest acted in bad faith by accepting free services while knowing Callow was offering them in order to maintain their future contractual relationship. Moreover, Callow alleged that Baycrest knew or ought to have known that Callow would not seek other winter maintenance contracts in reliance on the representations that Callow was providing satisfactory service and the contract would not be prematurely terminated. Accordingly, "[a]s a result of these misrepresentations and/or bad faith conduct, [Mr. Callow on behalf of Callow] did not bid on other tenders for winter maintenance contracts. [Baycrest is] now liable for Callow's damages for loss of opportunity" (A.R., vol. I, p. 45, at para. 30). Finally, Callow alleged that Baycrest was unjustly enriched by the free services it provided in the summer of 2013.
[ 16 ] Callow sought damages in the amount of $81,383.68 for breach of contract, an amount equivalent to the one year remaining on the winter maintenance agreement, damages for intentional interference with contractual relations, inducing breach of contract, and negligent misrepresentation. It also asked for damages in the amount of $5,000.00 for unjust enrichment, an amount equivalent to the "freebie" work, and pre‑ and post-judgment interest and costs on a substantial indemnity basis.
III. Prior Decisions
A. Ontario Superior Court of Justice (O'Bonsawin J.), 2017 ONSC 7095
[ 17 ] In her review of the circumstances of the dispute, the trial judge commented on the testimony of several key witnesses, concluding that Mr. Callow was a credible witness. In contrast, she found that Baycrest's witnesses — including a former property manager, as well as Ms. Zollinger and Mr. Peixoto — had "provided many exaggerations, over-statements and constantly provided comments contrary to the written evidence" (para. 11). The trial judge thus preferred Mr. Callow's version of events to that of Baycrest.
[ 18 ] At trial, Baycrest advanced two main submissions. First, it argued that, as a matter of simple contractual interpretation, clause 9 clearly and unambiguously states that it could terminate the contract for any reason by providing Callow with 10 days' notice in writing. Second, even though no cause had to be shown to invoke clause 9, Baycrest nonetheless argued that the evidence before the trial judge demonstrated that Callow's level of service did not comply with the contractual specifications and was not to its complete satisfaction.
(The judgment continues through extensive analysis of the duty of honest performance, the organizing principle of good faith, abuse of rights doctrine, and the measure of damages, in the majority reasons of Kasirer J. (paras. 19–120), the concurring reasons of Brown J. (paras. 121–182), and the dissenting reasons of Côté J. (paras. 183–238).)
Concurring Reasons (Brown J., Moldaver and Rowe JJ. concurring)
(paras. 121–182)
Dissenting Reasons (Côté J.)
I. Introduction
[ 183 ] I have read the reasons of my colleagues Kasirer J. and Brown J. I agree with Brown J. that the applicable legal standard is that of the duty of honest performance as formulated in Bhasin, which prohibits lying or otherwise knowingly misleading a contracting party about matters directly linked to the performance of the contract. However, unlike Brown J., I am of the view that the appeal should be dismissed. Callow's recourse cannot be based on a breach of the duty of honest performance.
II. Legal Framework
[ 184 ] The duty of honest performance is described in Bhasin as a simple requirement not to lie or knowingly mislead about matters directly linked to performance of the contract. The requirement that parties not lie is straightforward; however, the kind of conduct covered by the requirement that they not otherwise knowingly mislead each other is not. I agree with Kasirer J. and Brown J. that the law imposes neither a duty of loyalty or of disclosure nor a requirement to forego advantages flowing from the contract on a contracting party (see Kasirer J.'s reasons, at para. 61; Brown J.'s reasons, at para. 122). Absent a duty to disclose, it is far from obvious when exactly one's silence will knowingly mislead the other contracting party or at what point a permissible silence turns into a non‑permissible silence that may constitute a breach of contract. In any event, the duty of honest performance should remain clear and easy to apply.
[ 185 ] My colleagues have elaborated extensively on the content of the duty of honest performance. I am not sure that all these elaborations are necessary to resolve the present case. In my view, the most important issue in this appeal is a simple factual one: Did Baycrest materially contribute to Callow's mistaken belief through active conduct?
[ 186 ] Rather than approaching this case by extensively elaborating on the content of the duty, I prefer to focus on the actual findings of the trial judge and on the evidence in order to determine whether the record supports a finding of a breach of that duty.
[ 187 ] Although my colleagues rightly note that the duty of honest performance can be breached by silence, half-truths or omissions, they also acknowledge that silence does not by itself breach that duty. Both of my colleagues acknowledge, as they must, that a party to a contract has no obligation to disclose its intent to terminate (Kasirer J.'s reasons, at para. 61; Brown J.'s reasons, at paras. 130-31). In order to find that Baycrest breached its duty of honest performance, a reviewing court must be satisfied that Baycrest's active conduct — that is, active conduct other than the non-disclosure of the termination decision — created or reinforced a misapprehension about the performance of the contract.
[ 188 ] Whether or not a party has made a representation is a question of mixed fact and law (Brown J.'s reasons, at para. 137). In practice, this means a reviewing court can overturn such a finding only where there is a palpable and overriding error (Housen v. Nikolaisen, 2002 SCC 33, [2002] 2 S.C.R. 235, at para. 37). Here, I am not satisfied that the trial judge's findings support a conclusion that Baycrest's active conduct materially contributed to Callow's mistaken belief.
[ 189 ] The fact that Baycrest was aware of Callow's mistaken belief, as evidenced by Mr. Peixoto's July 17, 2013 email, is not enough to impose an obligation to speak. If mere awareness of the other party's mistaken belief triggers an obligation to speak, this would create a duty of disclosure, which is simply not part of the duty of honest performance.
[ 190 ] In order to find that Baycrest breached the duty of honest performance, one must also find that it actually lied or knowingly misled Callow through its active conduct. Passive acceptance of "freebie" work is not, by itself, active misleading conduct; a duty to refuse such work in order to correct a mistaken belief would be tantamount to a duty of disclosure, which does not exist under the law.
[ 191 ] As for the discussions about renewal, I disagree with my colleagues that those discussions materially contributed to Callow's mistaken belief. As I explain below, the evidence does not establish that Baycrest actively represented to Callow that the winter agreement would be renewed or that it was not at risk of being terminated.
[ 192 ] In sum, although Baycrest knew that Callow believed that the winter agreement would not be terminated, Baycrest did not make any representations to Callow that materially contributed to that mistaken belief. Baycrest may have been evasive and cavalier, but it did not lie to or knowingly mislead Callow in contravention of the duty of honest performance.
[ 193 ] I will first address my view of the legal framework before turning to the application of the duty of honest performance to the facts of this case.
[ 194 ] In Bhasin, Cromwell J. articulated the duty of honest performance as follows:
I would hold that there is a general duty of honesty in contractual performance. This means simply that parties must not lie or otherwise knowingly mislead each other about matters directly linked to the performance of the contract. This does not impose a duty of loyalty or of disclosure or require a party to forego advantages flowing from the contract; it is a simple requirement not to lie or knowingly mislead. [para. 73]
[ 195 ] As I read these words, the duty of honest performance is subject to an important limitation: the dishonesty must relate to "matters directly linked to the performance of the contract". This limitation excludes conduct that, although dishonest, is not directly linked to the performance of the contract.
[ 196 ] In Bhasin, Cromwell J. also said: "I do not think it is useful to analogize the duty of honest performance to tort doctrines such as misrepresentation or negligence. The duty of honest performance is a contractual doctrine. As such, it is not a stand-alone tort doctrine. Rather, it is a general doctrine of contract law that applies to all contracts as a matter of law" (para. 74).
[ 197 ] I note that the duty of honest performance as described by Cromwell J. is a limited duty. It forbids lying and knowingly misleading about matters directly linked to contractual performance. It does not impose a duty of good faith in a broad sense or require a party to be forthright.
[ 198 ] It must be borne in mind that all obligations flowing from the duty of honest performance are "negative" obligations (P. Daly, "La bonne foi et la common law: l'arrêt Bhasin c. Hrynew", in J. Torres-Ceyte, G.‑A. Berthold and C.‑A. M. Péladeau, eds., Le dialogue en droit civil (2018), 89, at pp. 101-2; see also Kasirer J.'s reasons, at para. 86). Extending the duty beyond that scope would "detract from . . . certainty in commercial dealings" (Bhasin, at para. 80).
[ 199 ] It must be borne in mind that all obligations flowing from the duty of honest performance are "negative" obligations (P. Daly, "La bonne foi et la common law: l'arrêt Bhasin c. Hrynew", in J. Torres-Ceyte, G.‑A. Berthold and C.‑A. M. Péladeau, eds., Le dialogue en droit civil (2018), 89, at pp. 101-2; see also Kasirer J.'s reasons, at para. 86). Extending the duty beyond that scope would "detract from . . . certainty in commercial dealings" (Bhasin, at para. 80).
[ 200 ] Therefore, silence cannot be considered dishonest within the meaning of Bhasin unless there is a positive obligation to speak. Such an obligation does not arise simply because a party to a contract realizes that his counterparty is operating under a mistaken belief.
[ 201 ] Absent a duty of disclosure, that is, absent any kind of free-standing positive obligation flowing from the duty of honest performance, a party to a contract has no obligation to correct his counterparty's mistaken belief unless the party's active conduct has materially contributed to it (see, in a different context, T. Buckwold, "The Enforceability of Agreements to Negotiate in Good Faith: The Impact of Bhasin v. Hrynew and the Organizing Principle of Good Faith in Common Law Canada" (2016), 58 Can. Bus. L.J. 1, at pp. 12-13).
[ 202 ] What constitutes a material contribution will obviously depend upon the context, which includes the nature of the parties' relationship (see Brown J.'s reasons, at para. 133) as well as the relevant provisions of the contract. But the reason underlying this requirement is a practical one that is consistent with Bhasin's emphasis on commercial expectations (at paras. 1, 34, 41, 60 and 62): parties that prefer not to disclose certain information — which they are entitled not to do — are not required to adopt a new line of conduct in their contractual relationship simply because they chose silence over speech.
[ 203 ] It cannot be that the law, on the one hand, allows contracting parties not to disclose information but, on the other hand, negates that possibility by imposing a standard of conduct that is at odds with the spontaneous attitudes — such as evasiveness and equivocation — parties might have when their conversations bear precisely on what they wish not to disclose.
[ 204 ] Even though parties who make that choice must be careful with what they say or do, especially if they become aware that their counterparties are operating under a mistaken belief, they should not be asked to behave as if their actions were being scrutinized under a microscope to determine whether they have contributed to that mistaken belief. Such a requirement would be unacceptable.
[ 205 ] In the context of a right to terminate a contract without cause, a party that intends to end an agreement does not have to convey hints in order to alert his counterparty that their business relationship is in danger. No duty of disclosure should mean no duty of disclosure.
[ 206 ] A party's awareness of his counterparty's mistaken belief will therefore not, in itself, trigger an obligation to speak unless the party has taken positive action that materially contributed to that belief. The active conduct and the mistaken belief must both pertain to contractual performance; otherwise, it could hardly be said that one has "knowingly misle[d] [the] other about matters directly linked to the performance of the contract" (Bhasin, at para. 73).
[ 207 ] In sum, the "minimum standard" of honesty imposed by the duty of honest performance has to be consistent with the other principles set out in Bhasin. It also has to be realistic and not overly formalistic. Absent a duty of disclosure, a party has no obligation to dissuade his counterparty from persisting in a mistaken belief. This does not mean that the party may induce or reinforce such a belief by significant positive actions or representations. There is an obligation to correct this mistaken belief if the party's active conduct has materially contributed to it.
III. Analysis
[ 208 ] Callow and Baycrest entered into two two-year contracts: a winter agreement covering mostly snow removal services for the period from November 1, 2012 to April 30, 2014 and a summer maintenance services agreement for the period from May 1, 2012 to October 31, 2013. The winter agreement, which is at issue here, contained the following provision:
- If the Contractor [i.e. Callow] fails to give satisfactory service to the Corporation [i.e. Baycrest] in accordance with the terms of this Agreement and the specifications and general conditions attached hereto or if for any other reason the Contractor's services are no longer required for the whole or part of the property covered by this Agreement, then the Corporation may terminate this contract upon giving ten (10) days' notice in writing to the Contractor, and upon such termination, all obligations of the Contractor shall cease and the Corporation shall pay to the Contractor any monies due to it up to the date of such terminations. [Emphasis added.]
(A.R., vol. III, at p. 10)
[ 209 ] In March or April 2013, Baycrest decided to terminate the winter agreement. On September 12, 2013, it gave Callow 10 days' notice that it was terminating the contract. In the meantime, Baycrest had learned that Callow was performing free extra landscaping work and that he was under the impression the winter agreement would not be terminated (trial reasons, 2017 ONSC 7095, at para. 48).
[ 210 ] It can easily be understood from these circumstances that Callow was "shocked" by the termination. Callow believed that, "if there was a problem, he would have expected [Baycrest] to bring it to his attention like [it] had done in the past" (trial reasons, at para. 49). Baycrest's behaviour was certainly discourteous and cavalier. Yet, that is not the question here. The question is whether Baycrest materially contributed to Callow's mistaken belief that the contract would not be terminated. If Baycrest did, then it had an obligation to correct that mistaken belief in accordance with its duty of honest performance. Otherwise, it had no obligation to disclose anything.
[ 211 ] Before our Court, Callow acknowledged that by entering into the winter agreement, he had taken the risk that Baycrest "may terminate [the contract], but only disclose the termination decision on 10 days' written notice" (transcript, at p. 11; see also C.A. reasons, 2018 ONCA 896, 429 D.L.R. (4th) 704, at para. 14). I am of the view that according to the terms of the winter agreement, Callow could have found himself in the exact same situation regardless of Baycrest's behaviour during the spring and summer of 2013. Such a possibility was in fact inherent in the contract he had bargained for.
[ 212 ] Callow essentially submits that Baycrest's active conduct led him to believe that the winter agreement was no longer at risk of being terminated despite the clear wording of the termination provision. He stresses the following points:
(1) Baycrest deliberately kept its decision secret because it did not want to jeopardize the performance of the summer agreement;
(2) Baycrest showed satisfaction with Callow's services;
(3) Callow had discussions with Mr. Peixoto and Mr. Campbell regarding the renewal of the winter agreement;
(4) Baycrest accepted Callow's "freebie" work; and
(5) Baycrest was aware of Callow's mistaken belief.
[ 213 ] In my view, the appeal should be dismissed.
[ 214 ] The trial judge's understanding of "active dishonesty" is tainted by an error of law. She did not consider the principle that, in order to amount to a breach of the duty of honest performance, any active dishonesty had to be "directly linked to the performance of the contract" (Bhasin, at para. 73). In assessing Baycrest's conduct, she did not inquire into whether Baycrest had "lie[d] or otherwise knowingly misle[d]" Callow about the exercise of its right to terminate the winter agreement for any other reason than unsatisfactory services. This explains why she wrongly insisted on, amongst other things, the need to "address the alleged performance issues" (para. 67) despite the fact that the winter agreement could be terminated even if Callow's services were satisfactory.
[ 215 ] Furthermore, although the trial judge seems to have been aware that there was no duty of disclosure (para. 60), she nonetheless found that Baycrest had acted in bad faith by "withholding the information to ensure Callow performed the summer maintenance services contract" (para. 65; see also para. 76). She never asked herself whether Baycrest had explicitly or implicitly said or done anything that could have misled Callow into thinking that the contract was at no risk of being terminated for any other reason than unsatisfactory services. It is clear from reading the trial judge's reasons as a whole that the "representations" she found had been made by Baycrest (at paras. 65, 67 and 76) were not directly linked to the performance of the winter agreement. In sum, the trial judge's misunderstanding of the applicable legal principles vitiated the fact-finding process.
[ 216 ] Baycrest had bargained for a right to terminate its winter agreement for any reason and at any time upon giving 10 days' notice. Its duty of honest performance did not require it to "forego" this undeniable "advantag[e] flowing from the contract" (Bhasin, at para. 73). It had no obligation to tell Callow about its decision to terminate the winter agreement until 10 days before the termination was to take effect, as the contract stipulated. Even after Baycrest became aware of Callow's mistaken belief, it had no obligation to refuse the "freebie" work Callow was performing on his own initiative or to correct this mistaken belief he was operating under. Such an obligation would have arisen only if Baycrest had contributed materially to that mistaken belief by inducing it or reinforcing it. In light of the evidence and the trial judge's findings, I am not convinced that Baycrest had done so.
[ 217 ] I do not have the same reading as my colleague Kasirer J. about certain of the trial judge's findings of fact (para. 100). These findings expressed in very broad terms should not be insulated from the reasons as a whole and from the evidence that was before the trial judge. For instance, my colleague writes that "Mr. Peixoto made statements to Mr. Callow suggesting that a renewal of the winter maintenance agreement was likely" (para. 95), and he considers that to be a "key finding" (para. 96). However, the trial judge's finding pertained to what Callow had thought, not to what Baycrest had said (trial reasons, at para. 41), which is something quite different. Indeed, as I demonstrate below, the evidence supporting this "key finding" shows that Callow's thoughts regarding a renewal of the winter agreement had nothing to do with what Baycrest said to him.
[ 218 ] I now turn to the application of the foregoing legal principles to the facts of this case.
A. Discussions About Renewal
[ 219 ] Callow argues that Baycrest materially contributed to his mistaken belief by discussing a possible renewal. Indeed, the renewal issue is central in this appeal. It is not disputed that unlike the contract at issue in Bhasin, the winter agreement did not contemplate any automatic renewal; it only contemplated termination. Since renewal was not a term of the winter agreement, it cannot be considered "performance of the contract" within the meaning of Bhasin. For Callow's claim to succeed, any breach of the duty of honest performance must pertain to termination.
[ 220 ] Both of my colleagues accept Callow's submission that it can be inferred from the discussions about renewal that the winter agreement was not in danger of termination. I would agree with such a proposition in the following circumstances: if one party leads another to believe that their contract will be renewed, it follows that the other party can reasonably expect their business relationship to be extended rather than terminated. But an inference to that effect cannot be drawn in the abstract. In order to infer that one party, through discussions about renewal, led the other party to think that there was no risk their existing agreement would be terminated, the inference-drawing process must obviously take into account the nature of the risk at stake and what was actually communicated during those discussions. Otherwise, the inference would entail a palpable and overriding error that would be subject to appellate review (Housen v. Nikolaisen, 2002 SCC 33, [2002] 2 S.C.R. 235, at paras. 22-23).
[ 221 ] Here, s. 9 of the winter agreement contemplated that the agreement might be terminated (1) for unsatisfactory services, or (2) for any other reason than unsatisfactory services. Did Baycrest, by discussing renewal, communicate anything that might have led Callow to believe there was no risk the winter agreement would be terminated for any other reason than unsatisfactory services? The trial judge described the discussions between the parties as follows:
During the spring and summer of 2013, Callow performed regular weekly grass cutting, garbage pick-up and was in discussions with the condominium corporations' board members to renew the contract for the following summer and also the winter maintenance services contract for a further two years. At this time, Callow had only completed year one of a two-year contract. The contract was supposed to remain in place for the winter of 2013-2014.
After his discussions with Mr. Peixoto and Mr. Campbell, Mr. Callow thought that he was likely to get a two-year renewal of his winter maintenance services contract and they were satisfied with his services. [Emphasis added; paras. 40-41.]
[ 222 ] The trial judge, who found Callow to be credible, relied on the following part of his testimony:
Q. Now is probably a good time to — well tell me about these discussions. Let's hear what discussions were you having.
A. Mostly with Joe [Peixoto], we discussed it, and he said "yeah, it looks good, I'm sure they'll be up for it, let me talk to them".
Q. Up for what?
A. A two-year renewal.
Q. All right. Anyone else?
A. Kyle Campbell I ran into once or twice on site and we had discussions as well too.
Q. Okay, and what was your impression of —of — I mean I suppose you already answered....
A. That I was likely going to be getting a two-year renewal, there was no reason not to, they were satisfied with the service, they were happy with it. [Emphasis added.]
(A.R., vol. II, at pp. 67-68)
[ 223 ] Apparently not much importance was attached to the renewal issue at trial. The amended statement of claim did not even address this issue; it instead focused on Baycrest's knowledge, Callow's "freebie" work and the provision of satisfactory services. Even though the trial judge did consider renewal, I note that her findings in this regard bore on Callow's mistaken belief that the winter agreement was likely to be renewed (at para. 41); they did not bear on anything Baycrest actually did or said that would have misled Callow into that belief.
[ 224 ] What Callow thought is one thing; what Baycrest said or did is another. According to Callow himself, Mr. Peixoto did not propose anything on behalf of Baycrest. Mr. Peixoto's statement that "I'm sure they'll be up for it, let me talk to them" (A.R., vol. II, at p. 67) clearly meant that despite his favorable opinion, he was not the one making the decision and that Baycrest had not even considered the mere possibility of a renewal at the time. It certainly could not be inferred from this statement that a renewal was likely. Callow's testimony does not suggest that he was misled into believing that Baycrest was actually contemplating a renewal — Mr. Peixoto's response instead presupposes the contrary — nor does it suggest that Baycrest did or said anything to negate the risk Callow took that his contract might be terminated for any other reason than unsatisfactory services. Indeed, Callow insisted that he had believed a renewal was likely because "there was no reason not to, they were satisfied with the service, they were happy with it" (A.R., vol. II, at p. 68).
[ 225 ] In his examination for discovery, Callow had given the same reason for thinking his winter agreement would be renewed, that is, because "there was no reason not to" (A.R., vol. II, at p. 49). He did not refer to his discussions with Mr. Peixoto or Mr. Campbell. When asked if anyone had told him that his contract would be renewed, he said he could not recall. The evidence does not establish that Mr. Peixoto or Mr. Campbell initiated the discussions about renewal. On the contrary, it suggests that Callow did. When cross-examined about his "freebie" work, Callow admitted that, although he was under the mistaken belief that his contract was likely to be renewed, he was in fact only "hopeful" that it would be. Nowhere in his testimony did he suggest that he had been given any information that could mislead him into believing that Baycrest was seriously contemplating a two-year renewal instead of termination.
[ 226 ] The trial judge referred to "active communications . . . between March/April and September 12, 2013, which deceived Callow" (para. 66), and to "representations in anticipation of the notice period" (para. 67; see also paras. 65 and 76). But those references must be read in light of the evidence and the reasons as a whole. Even though the trial judge made credibility findings against Mr. Peixoto and Mr. Campbell and credibility findings in favour of Callow, the evidence pertaining to renewal supports only a very limited number of inferences regarding termination.
[ 227 ] At most, it can be said that Mr. Peixoto and Mr. Campbell did not dissuade Callow from entertaining hopes when they had a chance to do so. But, and most importantly, they did not suggest that Baycrest was actually contemplating a continuation of their business relationship. If that had been the case, then I would agree that it might have been justifiable to infer that Callow had been led to believe there was no risk that his existing contract would be terminated before its term. But that was simply not the case here. In my view, the trial judge did not infer from the discussions about renewal that Baycrest had done or said anything to negate the risk that the winter agreement would be terminated for any other reason than unsatisfactory services. Had she made such an inference, it would be subject to appellate review, as it would not be supported by the evidence. Given the context discussed above, Mr. Peixoto's and Mr. Campbell's vague and evasive declarations did not materially contribute to Callow's mistaken belief that would have required Baycrest to disclose additional information.
B. Baycrest's Satisfaction With Callow's Services
[ 228 ] The trial judge placed great importance on the fact that Callow's services had been satisfactory and that Baycrest's conduct had given him no reason to think otherwise (paras. 22, 27, 29‑30, 34-36, 39, 41, 46-47 and 55). I note there is no finding that Baycrest communicated any particular sign of satisfaction pertaining to the performance of the winter agreement past March 19, 2013. That being said, there is nothing dishonest about Baycrest terminating the winter agreement after showing its satisfaction with the quality of Callow's work.
[ 229 ] Further, the parties had explicitly contemplated that Baycrest could terminate the winter agreement even if it was satisfied with Callow's performance, as the contract provided that Baycrest could exercise its termination right for any other reason than unsatisfactory services. Thus, positive feedback about Callow's services cannot justify Callow's mistaken belief that the contract would not be terminated.
C. Callow's Mistaken Belief That the Winter Agreement Would Remain in Effect
[ 230 ] The trial judge found that Baycrest had "continu[ed] to represent that the contract was not in danger" (paras. 65 and 76; see also para. 13). This finding was essentially grounded on the overall signs of satisfaction communicated by Baycrest, on its acceptance of the "freebie" work and on Callow's mistaken belief following the discussions pertaining to renewal. As I have already explained, nothing here required Baycrest to disclose its intent to terminate the winter agreement.
[ 231 ] What the trial judge did not find is also relevant. She did not find that Baycrest had decided to forego its right to terminate the winter agreement. She did not find that Baycrest had lied to Callow. She did not find that Baycrest had negated the risk taken by Callow that his contract would be terminated for any other reason than unsatisfactory services. Lastly, she did not clearly indicate why Callow so firmly believed "that his winter maintenance services contract would remain in place during the following winter" (para. 13).
[ 232 ] Callow's belief that there was no risk Baycrest would exercise its termination right was based on two things. First, on the positive feedback he had received regarding his services. In his words, Baycrest was "happy with it". However, this is not very relevant in a context in which Baycrest could terminate the winter agreement for any other reason than unsatisfactory services. Second, and most importantly, Callow's mistaken belief was based on an erroneous interpretation of the winter agreement.
[ 233 ] At trial, Callow testified that he was aware of the termination clause, but that he thought the two-year term made it unenforceable:
Q. . . . So, in that letter, there is a — a statement that the termination was in breach of the agreement. So, my question for you is, at that point in time what was your understanding, why was the termination in breach of the agreement?
A. Because they asked me, and we entered into a two year agreement, to provide services both summer and winter; and I did so at a reduced rate. I upheld my end of the bargain which was to perform that work at that reduced rate. They — and which I might add, I was not paid for, the landscaping and the final aspect of it, they were supposed to pay me. They didn't do it. And I continued to fulfill my contractual obligations. I expected nothing less than the same from them.
Q. So — so, when you — because you talk — but you knew that in the winter contract, there was that termination clause.
A. They had a clause written in there. I didn't believe it be enforceable because we had a two year contract. That's the whole idea to a two year contract. You have contract for two years. I provide services for two years and they pay me for those services. [Emphasis added.]
(A.R., vol. II, at p. 120; see also pp. 106-7.)
[ 234 ] Even though that was not the position he took in this Court, Callow's uninformed interpretation of the termination provision casts an important light on the reason why he did not believe there was a risk the winter agreement would be terminated for any other reason than unsatisfactory services. The evidence does not suggest that Baycrest said or did anything that could have negated that risk, nor does it suggest that Baycrest had anything to do with Callow's erroneous interpretation of the termination provision. I am therefore of the view that Baycrest was not required to correct Callow's mistaken belief by disclosing information it decided not to disclose.
IV. Conclusion
[ 235 ] The trial judge erred in concluding that Baycrest had to address performance issues or provide prompt notice prior to termination (para. 67). She did not inquire into whether Baycrest had made any representations that had misled Callow into thinking Baycrest would not terminate the winter agreement for any other reason than unsatisfactory services. In my view, the trial judge extended the ambit of the duty of honest performance in a way that was not consistent with the other principles set out in Bhasin.
[ 236 ] In sum, the narrow issue in this appeal comes down to this: Did Baycrest lie or otherwise knowingly mislead Callow into thinking that there was no risk it would exercise its right to terminate the winter agreement for any other reason than unsatisfactory services? There were no outright lies. Baycrest was aware of Callow's mistaken belief that his services would be required for the upcoming winter. But Baycrest never forewent the contractual advantage it had of being able to end the winter agreement at any time upon 10 days' notice. Nor did Baycrest say or do anything that materially contributed to Callow's mistaken belief that the winter agreement would not be terminated for any other reason than unsatisfactory services. Regardless of how its conduct is characterized, Baycrest had no obligation to correct Callow's mistaken belief.
[ 237 ] To be clear, the result I arrive at should not be interpreted as meaning that Baycrest's behaviour was appropriate or that Callow has no recourse. It means that Callow's recourse cannot be based on a breach of the duty of honest performance. The trial judge did in fact find that Baycrest had been unjustly enriched by the "freebie" work (at para. 77), but she stated that Callow had not provided evidence of his expenses. That question exceeds the scope of this appeal, however.
[ 238 ] I would therefore dismiss the appeal.
Appeal allowed with costs throughout, Côté J. dissenting.
Solicitors for the appellant: McCarthy Tétrault, Toronto; KMH Lawyers, Ottawa.
Solicitors for the respondents: Gowling WLG (Canada), Ottawa.
Solicitors for the intervener the Canadian Federation of Independent Business: Blake, Cassels & Graydon, Toronto.
Solicitors for the intervener the Canadian Chamber of Commerce: Torys, Toronto.

