In a construction lien reference involving multiple solar farm projects, the defendant brought a motion for security for costs against the plaintiff contractor.
The plaintiff corporation had ceased operations and possessed no assets other than potential recoveries from ongoing litigation, making any future costs judgment likely unenforceable.
The court held that the threshold under Rule 56.01(d) of the Rules of Civil Procedure was met and that the plaintiff failed to demonstrate that ordering security would be unjust.
Arguments relating to delay, counterclaims, and alleged defendant-caused impecuniosity were rejected or given limited weight.
Exercising its discretion and balancing proportionality concerns, the court ordered the plaintiff to post security for costs in the amount of $225,000.