The defendant moved for summary judgment to discharge a construction lien and certificate of action registered by the plaintiff.
The plaintiff failed to file responding materials and requested an adjournment, which was denied.
The court found that the plaintiff failed to perfect the lien within the 45-day statutory period under the Construction Lien Act.
As the lien had expired, the court granted the motion and ordered the lien discharged, awarding costs to the defendant.