Drainage petition declared invalid; costs of failed 10-year project apportioned among municipalities, petitioners, and conservation authority.
The Municipality of Bluewater brought a motion for directions regarding the proposed Ausable River Municipal Drain.
Following the withdrawal of several petitioners, the Referee determined that the third petition for the drain was no longer valid.
The Referee then apportioned the substantial costs incurred over the 10-year history of the failed project.
Costs for the first two petitions were assessed against the petitioners and the withdrawing municipality.
Costs related to environmental and cost-benefit studies were assessed against the Ausable Bayfield Conservation Authority, which had requested them.
The remaining costs were divided equally among the petitioners, the Municipality of Bluewater, and the Municipality of South Huron.