3 total
Substantial indemnity costs of $175,000 awarded to successful plaintiff due to defendants' unreasonable conduct.
Following a trial where the plaintiff successfully proved a construction lien and defeated the defendants' counterclaim, the court determined the costs and interest payable.
The plaintiff sought substantial indemnity costs of $225,504.45, while the defendants argued for $85,000.
The court awarded the plaintiff $175,000 in substantial indemnity costs, citing the defendants' unreasonable conduct, misleading evidence, and failure to accept multiple generous offers to settle.
The court also awarded prejudgment interest at the contractual rate of 25%.
Homeowners wrongfully repudiated renovation contract; contractor awarded $19,113.80 for unpaid work and extras.
The plaintiff contractor brought a construction lien action against the defendant homeowners for unpaid work and extras on a residential renovation project.
The defendants counterclaimed for damages, alleging the plaintiff abandoned the project and performed defective work.
The court found that the defendants wrongfully repudiated the contract without justification, as the alleged deficiencies did not meet the high threshold required for termination.
The plaintiff was awarded $19,113.80 for the balance of the contract price and approved extras, less credits for unfinished work, and the defendants' counterclaim was dismissed.
Motion to strike dismissed as claims of asset stripping and fraud were not barred by res judicata.
The moving parties (defendants) brought a motion under Rule 21.01(3) to strike paragraphs from the plaintiff's statement of claim, arguing the claims were barred by res judicata and abuse of process due to a prior construction lien action.
The plaintiff had previously obtained a default judgment on a counterclaim in the lien action and now alleged the moving parties stripped the corporate defendant's assets to make it judgment proof.
The court dismissed the motion, finding that the issues of fraud and asset stripping against the personal defendants were not and could not have been adjudicated in the prior lien action, as there was no judgment against the corporate defendant at that time.