The appellants appealed a trial judgment regarding the scope of contracted construction work and the costs of extras.
The Court of Appeal found no basis to interfere with the trial judge's findings of fact.
However, on the respondent's advice of a double counting error, the court allowed the appeal in part to reduce the judgment amount by $7,283.15 to $92,282.64, with corresponding adjustments to prejudgment interest.
Costs of the appeal were awarded to the respondent.