Tribunal adopted Minutes of Settlement resolving an appeal of a drainage works engineer's report.
The appellant appealed an engineer's report regarding the 8th Concession East Drain under sections 48 and 54 of the Drainage Act.
Prior to the hearing, the parties reached a settlement.
The Tribunal accepted the Minutes of Settlement, which amended the assessment schedule and relocated a borrow pit, and ordered the engineer and the municipality to modify the report, tender documents, and by-law accordingly.
Drainage appeal adjourned to defer to Referee's jurisdiction over related negligence claims.
The appellants appealed to the Ontario Drainage Tribunal regarding the 8th Concession East Drain.
The Tribunal noted that the appeal involved allegations of negligence and substandard work related to a 1991 repair, which were also the subject of a motion before the Referee.
To avoid duplicate proceedings and potentially conflicting decisions, the Tribunal adjourned the hearing and deferred to the Referee's jurisdiction to determine the necessity of the work, cost allocation, and liability.