The appellant appealed a decision by the Tarion Warranty Corporation denying her claim for compensation for a deposit paid to a home builder.
The appellant argued she had exercised her statutory right to rescind the agreement of purchase and sale (APS) and that the builder committed a fundamental breach by failing to set a delayed closing date and selling the home to another buyer.
The Tribunal found that the builder's unavoidable delay notices were invalid, meaning the original critical dates applied, and the appellant's termination notice was provided after the termination period had expired.
Furthermore, applying the Spirent factors, the Tribunal held that the builder's failure to set a delayed closing date did not constitute a fundamental breach, as it did not deprive the appellant of substantially the whole benefit of the APS.
The appeal was dismissed.