This endorsement from a case conference provides updates on the progress of multiple consolidated actions.
Key discussions included the status of document production between Carillion and the City of Toronto, scheduled motions by the City against subcontractors for document production, and a hearing for construction lien matters.
The endorsement also addressed NORR Limited's statement of claim against the City, the participation of various subcontractors in mediation, and Metrolinx's contemplation of motions for particulars and to strike against the City's third-party claim.
The court set a timeline for Metrolinx to decide on its participation in the upcoming mediation, contingent on the outcome of its motion for particulars.