The plaintiff contractor sued the defendant homeowner for unpaid extras on a kitchen renovation project.
The defendant counter-claimed for damages, alleging defective and incomplete work.
The court found that the defendant prematurely and without good cause terminated the contract.
The court accepted the plaintiff's evidence that the extras were authorized and necessary due to structural defects discovered during the renovation.
The plaintiff was awarded $5,090 for the extras, and the defendant's counter-claim was dismissed.