4 total
Plaintiff awarded $35,000 in partial indemnity costs following successful construction lien trial.
Following a trial where the plaintiff was awarded judgment for $86,244.38 on a construction lien claim, the court determined the issue of costs.
The plaintiff sought partial indemnity costs of $69,701.77, while the defendant, despite being unsuccessful, sought substantial indemnity costs arguing he was the more successful party on the major trial issues.
The court rejected the defendant's argument, finding no basis to award costs to an unsuccessful defendant.
Applying the factors under section 86 of the Construction Lien Act and Rule 57.01, the court awarded the plaintiff $38,000 in costs, less a $3,000 set-off for a prior motion, resulting in a net costs award of $35,000 to the plaintiff.
Contractor awarded $86,244.38 on construction lien after court resolves disputes over contract scope, extras, and payments.
The plaintiff contractor registered a construction lien for unpaid services and materials relating to the construction of a new residential home.
The defendant owner disputed the claim, arguing that the contractor abandoned the project, overcharged for extras that were part of the base contract, and left deficient work.
The court interpreted the fixed-price contract to determine the base scope of work, finding that some claimed extras were included in the base price while others were compensable.
After accounting for proven payments, loan credits, and a minor set-off for incomplete work, the court found the owner breached the contract by failing to pay.
The contractor was awarded a valid lien and judgment for $86,244.38 plus pre-judgment interest.
Leave to appeal granted to determine if declaratory relief claim circumvented the expired limitation period.
The defendants sought leave to appeal an order dismissing their motion for summary judgment and permitting the plaintiff to amend its statement of claim to seek only declaratory relief regarding a 5% share ownership.
The court granted leave to appeal, finding good reason to doubt the correctness of the motion judge's order because the declaratory relief sought was arguably ancillary to statute-barred consequential relief.
The court also found the parameters of section 16(1)(a) of the Limitations Act to be a matter of general importance warranting appellate review.
Summary judgment Motion dismissed
The plaintiff, a gasoline wholesaler, brought a motion for partial summary judgment against one of the defendants, Gill Rauni Petroleum Inc. (GRP), for breach of contract regarding unpaid petroleum products.
The plaintiff claimed over $117,000.
The court found that the plaintiff failed to provide sufficient evidence to establish breach of contract, orders, deliveries, or a full accounting of outstanding amounts, thus failing to "put its best foot forward." Applying the principles of summary judgment, the court determined that genuine issues requiring a trial existed and that the evidentiary record was insufficient for dispositive findings.
Furthermore, as the litigation would proceed to trial against another defendant regardless, granting partial summary judgment risked duplicative proceedings and inconsistent findings, making it not in the interest of justice.
The motion was dismissed, and the defendant GRP was awarded costs.