Appeal allowed and provisional consent granted for three new building lots based on parties' settlement.
The applicant appealed the Township's deferral/denial of an application for consent to sever a rural property into three new building lots.
Prior to the hearing, the parties reached a settlement.
Based on the uncontroverted expert planning evidence of the Township's planner, the Tribunal found the proposed severance and conditions were consistent with the Provincial Policy Statement, conformed to the applicable official plans, and represented good planning.
The appeal was allowed and provisional consent was granted subject to the agreed-upon conditions.
OLTOntario Land TribunalMay 15, 2025