The applicant subcontractor sought an order requiring the respondent general contractor to arbitrate a delay claim separately from the general contractor's delay claim against the owner.
The court dismissed the application, finding that the subcontract explicitly required disputes relating to the owner to be consolidated and disposed of in the same proceedings.
The court also found that the general contractor had used 'best efforts' to advance the global delay claim against the owner in accordance with the prime contract.