An appeal from a trial judgment concerning a construction contract dispute.
The appellants challenged the trial judge's findings regarding responsibility for drywall deficiencies and the labour rate credited to the appellant.
The appellate court found the trial judge's determination that the appellant assumed responsibility for drywall installed by third parties was fully supported by evidence.
The court also found no error in the trial judge's assessment of the labour rate issue.
The appeal was dismissed with costs awarded to the respondent.