Tribunal approves settlement for 50-unit townhouse development, withholding final order pending engineering and demolition conditions.
The applicant appealed the City of Toronto's failure to make a decision on a Zoning By-law Amendment application to facilitate a 50-unit townhouse development.
The parties reached a settlement and presented revised planning instruments to the Tribunal.
Relying on uncontradicted expert planning evidence, the Tribunal found the proposal consistent with the Provincial Planning Statement and in conformity with the City's Official Plan.
The appeal was allowed in part, and the draft Zoning By-law Amendment was approved in principle, with the final order withheld pending the satisfaction of several conditions, including the submission of finalized engineering reports and a rental housing demolition application.
OLTOntario Land TribunalJan 22, 2026