Private school development approved subject to increased 30m wetland buffers and further wildlife habitat studies.
The South Bracebridge Environmental Protection Group appealed the Town of Bracebridge's approval of an Official Plan Amendment and Zoning By-law Amendment to facilitate the development of a private school complex.
The Tribunal found that the proposed development is consistent with the Provincial Policy Statement and conforms with the applicable Official Plans, provided that the minimum buffer for wetlands and watercourses is increased from 15m to 30m.
The Tribunal also required the inclusion of a holding symbol that can only be lifted after site-specific environmental impact statements, including comprehensive amphibian and bat surveys, demonstrate no negative impacts on significant wildlife habitat.
The appeal was allowed in part to implement these amendments.
OLTOntario Land TribunalOct 27, 2023