Subcontractor's construction lien discharged because it was not preserved within the 60-day statutory period.
The moving party defendants sought to discharge a construction lien registered by the plaintiff subcontractor and to dismiss the plaintiff's action.
The court found that the plaintiff had no direct contract with the owner defendants, only with the general contractor, and that it had failed to preserve its lien within the 60 days required by the Construction Act after completing its work.
The court ordered the lien discharged, the bond returned, and the action dismissed.