2 total
Appeals dismissed and order revoked following settlement regarding replacement of sewage works.
The appellants appealed an order requiring them to perform work on sewage works.
The parties reached a settlement wherein the appellants replaced the sewage system under the Ontario Building Code, obtained necessary permits, and removed components from the shore road allowance.
The Tribunal found the proposed revocation of the order consistent with the Ontario Water Resources Act and the public interest, revoked the order, and dismissed the appeals.
Adjournment and interim stay of environmental order granted on consent pending building permit application.
The appellants requested a hearing regarding an order requiring them to perform work with respect to sewage at a property.
The parties jointly requested an adjournment of the hearing and an interim stay of the order to allow the appellants to obtain a building permit for a sewage system from the municipality.
The Tribunal granted the adjournment and interim stay on consent, finding that the proposed terms met the statutory requirements and would ensure environmental concerns were addressed on an interim basis.