7 total
The court partially granted a motion to dismiss duplicative claims and ordered the consolidation of related construction and debt actions to ensure judicial economy.
The defendants moved to dismiss or stay the plaintiff's action under Rule 21.01(3) due to pending related proceedings.
The court rejected arguments of res judicata and issue estoppel, finding no final determinations had been made.
It allowed the action to proceed against one defendant, Vilson Da Silva, as the claims were distinct and could not be brought in the existing lien action due to the Construction Lien Act.
However, claims against Leblon Carpentry were dismissed for lack of factual basis, and claims against Leblon Drywall were dismissed (without prejudice) as they were duplicative of an existing counterclaim in the lien action and contrary to the purpose of the Construction Lien Act.
To ensure judicial economy and avoid multiplicity of actions, the court ordered the transfer of a related Barrie action to Brampton and directed that all three interconnected actions be tried together or sequentially.
A motion to discharge certificates of pending litigation was dismissed as an abuse of process.
The defendants brought a motion to discharge Certificates of Pending Litigation (CPLs), alleging the plaintiff fraudulently obtained them by withholding a financial statement from a prior matrimonial file.
The plaintiff brought a cross-motion seeking to dismiss the defendants' motion as an abuse of process.
The court found that the defendants had prior knowledge of the "material and crucial" evidence but consciously chose not to present it at the original CPL motion.
Consequently, the court granted the plaintiff's motion, dismissing the defendants' motion to discharge the CPLs on the basis of abuse of process.
The court also criticized the defendants' litigation strategy and ordered that no further motions could be brought without leave of the Commercial List Team Lead.
Condominium noise and nuisance application dismissed for lack of objective evidence; applicant ordered to pay costs.
The applicant, a condominium unit owner, applied to the Condominium Authority Tribunal claiming that the respondents, who own the unit above hers, were causing unreasonable noise and nuisance, including heavy footsteps, banging, and overwatering balcony plants.
The respondents denied the allegations, asserting they were only carrying out normal daily activities and that the applicant was harassing them.
The Tribunal found insufficient objective evidence to conclude that the respondents were creating unreasonable noise or nuisance in violation of the Condominium Act or the condominium's governing documents.
The application was dismissed, and the applicant was ordered to pay $210 in costs to the intervenor condominium corporation for unreasonable behavior during the proceeding.
Condominium owner ordered to comply with noise rules and pay full indemnity costs for repeated violations.
The applicant condominium corporation sought an order requiring the respondent owner to comply with its noise rules and to pay costs incurred in enforcing compliance.
The respondent repeatedly played loud music with heavy bass late at night, generating numerous security complaints, and ignored multiple warning letters from management and legal counsel.
The Condominium Authority Tribunal found the respondent in violation of the noise rules and section 117(2) of the Condominium Act, 1998.
The Tribunal ordered the respondent to comply with the rules and awarded the corporation full indemnity for its legal costs and pre-litigation legal expenses, totaling $9,848.51.
A 1965 nationalization agreement effected an assignment of a 1926 power contract, allowing Hydro-Québec to pass statutory levies onto the purchaser.
A forest products company challenged the right of a state-owned electricity distributor to invoke a price adjustment clause in a 1926 power supply contract, arguing that the distributor was not a party to that contract.
The majority held that a 1965 bilateral contract between the distributor and the original contracting party effected a temporally limited assignment of the 1926 contract, with the assigned party's advance consent validly given in the original agreement.
As a result, the distributor was entitled to pass on to the forest products company the taxes and charges levied upon it by provincial legislation as increases in the cost of electricity generated from water power.
The dissent maintained that the trial judge had committed no reviewable error in finding that the 1965 contract created a mandate rather than an assignment, and that the Court of Appeal should not have intervened by analyzing the contract on a theory never advanced at trial.
Medical malpractice action dismissed; physicians met standard of care in diagnosing and surgically removing cardiac mass.
The plaintiff underwent open-heart surgery to remove a mass that was pre-operatively diagnosed as a likely myxoma (tumor) but was post-operatively confirmed to be a thrombus (blood clot).
The plaintiff brought a medical negligence action against the involved cardiologists, cardiac surgeon, and cardiac anaesthetist, alleging they breached the standard of care by failing to diagnose the mass as a clot and treat it medically, and by failing to obtain informed consent.
The Superior Court of Justice dismissed the action, finding that the physicians met the standard of care in their differential diagnosis and treatment plan, as the mass had unusual features suggestive of a tumor and required surgical removal regardless.
The court also found that causation was not established and that informed consent was properly obtained.
Child support Claim dismissed
The applicant mother sought child support from the respondent father under the Inter-Jurisdictional Support Orders Act.
The father disputed the table amount, retroactive application, and contribution to special expenses, primarily claiming undue hardship due to high debts, potential job loss, and access costs.
The court rejected the father's undue hardship claim, finding his debts were not incurred as per the Guidelines, his financial support of other adults did not trump child support, and he did not exercise access.
The court ordered child support based on the father's income, retroactive to February 2018, but declined to order contributions for daycare or soccer expenses due to insufficient evidence and the non-extraordinary nature of the soccer expense.
The father was ordered to maintain the child as a beneficiary under his medical/dental plan.