The appellant contracted with the respondent for the installation of a high-efficiency gas furnace and air-conditioning unit.
Dissatisfied with the location of the ductwork and other elements, the appellant refused to pay the balance owing.
The respondent successfully sued in Small Claims Court for the unpaid balance.
The appellant appealed to the Divisional Court.
The court dismissed the appeal, finding no substantial error by the trial judge, noting that the appellant had left the specific location of the materials to the professionals and the contract made no specific provision for it.