The parties, two closely held private companies owned by brothers, disputed an unwritten agreement allowing the plaintiff to extract aggregate and timber from the defendants' land.
The defendants brought a motion to discharge a construction lien registered by the plaintiff, while the plaintiff brought a motion to preserve harvested wood and blasted rock on the property.
The court granted the defendants' motion to discharge the lien, finding no lienable services were provided and the lien was not preserved in time.
The court also granted the plaintiff's motion for an interim preservation order, finding the test under Rule 45.01 was met.