Committee of Adjustment
Comité de dérogation
DECISION
CONSENT/SEVERANCE AND MINOR VARIANCE
Panel: 2 - Suburban
Files: D08-01-25/B-00288 to D08-01-25/B-00290, D08-02-25/A-00279
Applications: Consent under section 53 of the Planning Act, Minor Variance under section 45 of the Planning Act
Applicants: A. Falbo and D. Derkzen
Property Address: 1781 Queensdale Avenue
Ward: 10 - Gloucester-Southgate
Legal Description: Lots 880 to 885, Registered Plan 326 and Part of Lane, Registered Plan 326
Zoning: R1WW
Zoning By-law: 2008-250
Heard: February 3, 2026, in person and by videoconference
APPLICANTS’ PROPOSAL AND PURPOSE OF THE APPLICATIONS
1The Applicants want to subdivide their property into three separate parcels of land to construct two, two-storey detached dwellings, as shown on plans filed with the Committee. The existing detached dwelling is to remain.
CONSENT REQUIRED:
2The Applicants seek the Committee of Adjustment’s consent to sever land. The property is shown as Parts 1 to 3 on a Draft 4R-Plan filed with the applications and the separate parcels will be as follows:
Table 1 Proposed Parcels
| File No. | Frontage | Depth | Area | Part No. | Building |
|---|---|---|---|---|---|
| B-00288 | 15.60 m | 30.39 m | 474.07 sq. m | 1 | Proposed dwelling |
| B-00289 | 18.61 m | 30.40 m | 566.49 sq. m | 2 | Existing dwelling 1781 Queensdale Avenue |
| B-00290 | 11.30 m | 30.43 m | 343.94 sq. m | 3 | Proposed dwelling |
3The proposal does not comply with the Zoning By-law and therefore minor variance applications have also been filed.
REQUESTED VARIANCE
4The Applicants seek the Committee of Adjustment’s authorization for a minor variance from the Zoning By-law as follows:
A-00279: Part 3 on draft 4R-Plan, proposed two-storey detached dwelling:
a) To permit a reduced lot area of 343.94 square metres, whereas the By-law requires a minimum lot area of 450 square metres.
5The property is not the subject of any other current application under the Planning Act.
PUBLIC HEARING
Oral Submissions Summary
6Michael Segreto, agent for the Applicant, and City Planner Dylan Geldart were present.
7There were no objections to granting this unopposed application as part of the Panel’s fast-track consent agenda.
DECISION AND REASONS OF THE COMMITTEE:
- CONSENT APPLICATION GRANTED
- MINOR VARIANCE APPLICATIONS GRANTED
Consent Application Must Satisfy Statutory Tests
8Under the Planning Act, the Committee has the power to grant a consent if it is satisfied that a plan of subdivision of the land is not necessary for the proper and orderly development of the municipality. Also, the Committee must be satisfied that an application is consistent with the Provincial Planning Statement, 2024, and has regard for matters of provincial interest under section 2 of the Act, as well as the following criteria set out in subsection 51(24):
Criteria
(24) In considering a draft plan of subdivision, regard shall be had, among other matters, to the health, safety, convenience, accessibility for persons with disabilities and welfare of the present and future inhabitants of the municipality and to,
a) the effect of development of the proposed subdivision on matters of provincial interest as referred to in section 2;
b) whether the proposed subdivision is premature or in the public interest;
c) whether the plan conforms to the official plan and adjacent plans of subdivision, if any;
d) the suitability of the land for the purposes for which it is to be subdivided;
d.1) if any affordable housing units are being proposed, the suitability of the proposed units for affordable housing;
e) the number, width, location and proposed grades and elevations of highways, and the adequacy of them, and the highways linking the highways in the proposed subdivision with the established highway system in the vicinity and the adequacy of them;
f) the dimensions and shapes of the proposed lots;
g) the restrictions or proposed restrictions, if any, on the land proposed to be subdivided or the buildings and structures proposed to be erected on it and the restrictions, if any, on adjoining land;
h) conservation of natural resources and flood control;
i) the adequacy of utilities and municipal services;
j) the adequacy of school sites;
k) the area of land, if any, within the proposed subdivision that, exclusive of highways, is to be conveyed or dedicated for public purposes;
l) the extent to which the plan’s design optimizes the available supply, means of supplying, efficient use and conservation of energy; and
m) the interrelationship between the design of the proposed plan of subdivision and site plan control matters relating to any development on the land, if the land is also located within a site plan control area designated under subsection 41 (2) of this Act or subsection 114 (2) of the City of Toronto Act, 2006. 1994, c. 23, s. 30; 2001, c. 32, s. 31 (2); 2006, c. 23, s. 22 (3, 4); 2016, c. 25, Sched. 4, s. 8 (2).
Minor Variance Applications Must Satisfy Statutory Four-Part Test
9The Committee has the power to authorize a minor variance from the provisions of the Zoning By-law if, in its opinion, the application meets all four requirements under subsection 45(1) of the Planning Act. It requires consideration of whether the variance is minor, is desirable for the appropriate development or use of the land, building or structure, and whether the general intent and purpose of the Official Plan and the Zoning By-law are maintained.
Evidence
10Evidence considered by the Committee included all oral submissions made at the hearing, as highlighted above, and the following written submissions held on file with the Secretary-Treasurer and available from the Committee Coordinator upon request:
- Applications and supporting documents, including a cover letter, letters of support, parcel abstract, plans, tree information, photo of the posted sign, and a sign posting declaration.
- City Planning Report received January 29, 2026, with no concerns.
- South Nation Conservation Authority email dated January 26, 2026, with no objections.
- Hydro Ottawa email dated January 28, 2026, with comments.
- Ottawa-Carleton District School Board email dated January 23, 2026, with comments.
- Ottawa International Airport Authority email dated February 2, 2026, with comments.
Effect of Submissions on Decision
11The Committee of Adjustment considered all written and oral submissions relating to the applications in making its decision and granted the applications.
12The Committee notes that the City’s Planning Report raises “no concerns” regarding the applications, subject to the requested conditions agreed to by the Applicant’s agent.
13Based on the evidence, the Committee is satisfied that the proposal is consistent with the Provincial Planning Statement, 2024, that promotes building homes, sustaining strong communities; providing infrastructure and public service facilities in an efficient manner while accommodating projected needs; the wise use and management of resources; and, protecting public health and safety.
14The Committee is also satisfied that the proposal has adequate regard to matters of provincial interest, including the orderly development of safe and healthy communities; the appropriate location of growth and development; and the protection of public health and safety.
15Additionally, the Committee is satisfied that a plan of subdivision of the land is not necessary for the proper and orderly development of the municipality.
16Moreover, the Committee is satisfied that the proposal has adequate regard for the criteria specified under subsection 51(24) of the Planning Act and is in the public interest.
17Based on the evidence, the Committee is also satisfied that the requested variance meets all four requirements under subsection 45(1) of the Planning Act.
18The Committee also finds that the requested variance maintains the general intent and purpose of the Official Plan because the proposal respects the character of the neighbourhood.
19In addition, the Committee finds that the requested variance maintains the general intent and purpose of the Zoning By-law because the proposal represents orderly development that is compatible with the surrounding area.
20Moreover, the Committee finds that the requested variance is minor, because they will not create any unacceptable adverse impact on abutting properties or the neighbourhood in general.
21THE COMMITTEE OF ADJUSTMENT ORDERS that the consent applications are granted and the provisional consent is to be given, subject to the conditions set out in Appendix A to this decision.
22THE COMMITTEE OF ADJUSTMENT ALSO ORDERS that the requested minor variance application is granted and the variance to the Zoning By-law is authorized.
"Fabian Poulin" FABIAN POULIN VICE-CHAIR
Absent JAY BALTZ MEMBER
"George Barrett" GEORGE BARRETT MEMBER
"Heather MacLean" HEATHER MACLEAN MEMBER
"Julianne Wright" JULIANNE WRIGHT MEMBER
I certify this is a true copy of the Decision of the Committee of Adjustment of the City of Ottawa, dated February 13, 2026
“Michel Bellemare” MICHEL BELLEMARE SECRETARY-TREASURER
NOTICE OF RIGHT TO APPEAL
To appeal this decision to the Ontario Land Tribunal (OLT), a completed appeal form and the filing fee must be submitted via one of the below options and must be received no later than 3:00 p.m. on March 5, 2026.
- OLT E-FILE SERVICE – An appeal can be filed online through the E-File Portal . First-time users will need to register for a My Ontario Account. Select [Ottawa (City): Committee of Adjustment] as the Approval Authority. To complete the appeal, fill in all the required fields and provide the filing fee by credit card.
- BY EMAIL - Appeal packages can be submitted by email to cofa@ottawa.ca. The appeal form is available on the OLT website at Forms | Ontario Land Tribunal. Please indicate on the appeal form that payment will be made by credit card.
- IN PERSON – Appeal packages can be delivered to the Secretary-Treasurer, Committee of Adjustment, 101 Centrepointe Drive, 4th floor, Ottawa, Ontario, K2G 5K7. The appeal form is available on the OLT website at Forms | Ontario Land Tribunal. In person payment can be made by certified cheque or money order made payable to the Ontario Minister of Finance, or by credit card. Please indicate on the appeal form if you wish to pay by credit card.
Please note only one of the above options needs to be completed. If your preferred method of appeal is not available at the time of filing, the appeal must be filed with one of the other two options.
The Ontario Land Tribunal has established a filing fee of $400.00 per type of application with an additional filing fee of $25.00 for each secondary application.
Only the applicant, the Minister or a specified person or public body that has an interest in the matter may appeal the decision to the Ontario Land Tribunal. A “specified person” does not include an individual or a community association.
There are no provisions for the Committee of Adjustment or the Ontario Land Tribunal to extend the statutory deadline to file an appeal. If the deadline is not met, the OLT does not have the authority to hold a hearing to consider your appeal.
If you have any questions about the appeal process, please visit File an Appeal | Ontario Land Tribunal
NOTICE TO APPLICANTS
Should a Development Agreement be required, such request should be initiated 30 working days prior to lapsing date of the consent and should include all required documentation including that related to transfers, easements, and postponements, and all approved technical studies. If you do not fulfill the conditions of provisional consent within the two-year period, the Planning Act provides that your application “shall be deemed to be refused”.
Ce document est également offert en français.
Committee of Adjustment City of Ottawa Ottawa.ca/CommitteeofAdjustment cofa@ottawa.ca 613-580-2436
Comité de dérogation Ville d’Ottawa Ottawa.ca/Comitedederogation cded@ottawa.ca 613-580-2436
APPENDIX “A”
The Owner(s) provide evidence that the accompanying minor variance application D08-02-25/A-00279 has been approved, with all levels of appeal exhausted.
That the Owner(s) submit a request for municipal addresses for each parcel, as required, to be assigned by the City, to the satisfaction of the Chief Building Official, or their designate. Confirmation of the assigned municipal addresses shall be provided in writing from Municipal Addressing, Building Code Services, to the Committee.
That the Owner(s) satisfy the requirements of Hydro Ottawa with respect to the relocation of the existing overhead services or grant an easement as required, the consent to which is hereby granted.
That the Owner(s) provide evidence to the satisfaction of the Chief Building Official, or designate, that the existing detached garage and shed been demolished or relocated under the authority of a building permit.
That the Owner(s) satisfies the Chief Building Official, or designate, by providing design drawings or other documentation prepared by a qualified designer, that as a result of the proposed severance on Draft R-plan shall comply with the Ontario Building Code, O. Reg. 332/12 as amended, in regard to the limiting distance along the proposed property line easterly and westerly sides are affected. If necessary, a building permit shall be obtained from Building Code Services for any required alterations.
That the Owner(s) provide evidence, to the satisfaction of the Manager of Development Review All Wards, Planning, Development and Building Services Department, that each existing parcel has its own independent storm, sanitary and water services connected to City infrastructure and that these services do not cross the proposed severance line. If they do cross or are not independent, the Owner(s) will be required, at their own cost, to relocate the existing services or construct new services from the City sewers/watermain. Notice shall be provided in writing to the Committee from the Department confirming this condition has been fulfilled.
That the Owner(s) provide a Stormwater Management Report, prepared by a Professional Civil Engineer, licensed in the Province of Ontario, demonstrating a design for post-development stormwater peak flows that are controlled to pre-development peak flows for all stormwater events up to and including the 100 year storm event. The report shall be to the satisfaction of and approved by the Manager of Development Review All Wards Branch within Planning, Development and Building Services Department, or their designate.
If the Stormwater Management Report includes infiltration techniques, the Owner(s) must provide a supporting Geotechnical Brief prepared by a Professional Civil Engineer licensed in the Province of Ontario, for approval by the Manager of Development Review All Wards Branch within Planning, Development and Building Services Department, or their designate.
The Owner(s) shall enter into a Development Agreement with the City to construct the required stormwater system, which may include required securities. A copy of the Agreement and written confirmation from City Legal Services that it has been registered on title, shall be forwarded to the Committee of Adjustment.
If applicable, the Owner(s) shall obtain all necessary approvals from the Ontario Ministry of Environment, Conservation and Parks.
That the Owner(s) provide proof that a grading and drainage plan, prepared by a qualified Civil Engineer, licensed in the Province of Ontario, an Ontario Land Surveyor or a Certified Engineering Technologist, delineating the existing and proposed grades for both the severed and retained lands has been provided to the satisfaction of the Manager of Development Review All Wards Branch within Planning, Development and Building Services Department, or their designate.
That the Owner/Applicant(s) provide a tree planting plan, prepared to the satisfaction of the Manager of Development Review All Wards Branch within Planning, Development and Building Services Department, or their designate, showing the location(s) and species or ultimate size of at least one new tree (50 mm caliper) per lot, in addition to any compensation trees required under the Tree Protection By-law.
That the Owner/Applicant(s) enter into a Development Agreement or a Letter of Undertaking (LOU) with the City of Ottawa, at the expense of the Owner/Applicant(s), and to the satisfaction of the Manager of Development Review All Wards Branch within Planning, Development and Building Services Department, or their designate. A development agreement is to be registered on title of the property (where applicable). The agreement/LOU will include the tree protection and mitigation requirements detailed in the Tree Protection By-law and the approved Tree Information Report (or any approved revisions), and associated securities for tree protection. The securities, which will be based on the value of the tree(s) to be protected (Tree #1) shall be retained for two (2) years following issuance of a final occupancy permit, and thereafter returned to the owner only upon the City having received a report from an arborist confirming that the identified tree(s) is/are healthy, retainable, and remain(s) structurally stable.
That the Owner/Applicant(s) provide Grading, Servicing, & Site plan(s) with the proposed elements/structures (driveways, parking, retaining walls, projections, services, etc.) designed and located based on the least impact to protected trees and tree cover, as well as a revised Tree Information Report reflecting these changes to the satisfaction of the Manager of Development Review All Wards Branch within Planning, Development and Building Services Department, or their designate.
The Owner must convey to the City, at no cost to the City, an unencumbered corner sight triangle measuring 3 metres by 3 metres, at the intersection of Queensdale and Sixth Street. The corner sight triangle must be determined by legal survey. The Owner shall provide a reference plan for registration, indicating the corner sight triangle, to the City Surveyor for review and approval prior to its deposit in the Land Registry Office. Such reference plan must be tied to the Horizontal Control Network in accordance with the municipal requirements and guidelines for referencing legal surveys. The Owner(s) must provide to the City Surveyor a copy of the Committee of Adjustment Decision and a draft Reference Plan that sets out the required corner sight triangle. The Committee shall be provided written confirmation from City Legal Services that the transfer of the corner sight triangle to the City has been registered. All costs shall be borne by the Owner.
That the Owner(s) file with the Committee a copy of the registered Reference Plan prepared by an Ontario Land Surveyor registered in the Province of Ontario, and signed by the Registrar, confirming the frontage and area of the severed land. If the Registered Plan does not indicate the lot area, a letter from the Surveyor confirming the area is required. The Registered Reference Plan must conform substantially to the Draft Reference Plan filed with the Application for Consent to the satisfaction of the Secretary-Treasurer of the Committee of Adjustment or their designate.
That upon completion of the above conditions, and within the two-year period outlined above, the Owner(s) file with the Committee, the “electronic registration in preparation documents” for a severance for which the Consent is required to the satisfaction of the Secretary-Treasurer of the Committee of Adjustment or their designate.