Ontario Land Tribunal
Tribunal ontarien de l’aménagement du territoire
ISSUE DATE: January 30, 2026
CASE NO.: OLT-24-001025
PROCEEDING COMMENCED UNDER subsection 22(7) of the Planning Act, R.S.O. 1990, c. P. 13, as amended.
Applicant/Appellant: 668390 Ontario Ltd. and 829426 Ontario Inc.
Subject: Request to amend the Official Plan – Failure to adopt the requested amendment
Description: To permit a mixed-use building consisting of nine high-rise buildings up to 40 storeys totaling 3,965 units and a linear park
Reference Number: COPA2024-0001
Property Address: 0 Prince William Boulevard; 1800 and 1850 Bowmanville Avenue
Municipality/UT: Clarington/Durham
OLT Case No: OLT-24-001025
OLT Lead Case No: OLT-24-001025
OLT Case Name: 668390 Ontario Ltd. et al. v. Clarington (Municipality)
PROCEEDING COMMENCED UNDER section 34(11) of the Planning Act, R.S.O. 1990, c. P. 13, as amended.
Applicant/Appellant: 668390 Ontario Ltd. and 829426 Ontario Inc.
Subject: Application to amend the Zoning By-law – Refusal or neglect to make a decision
Description: To permit a mixed-use building consisting of nine high-rise buildings up to 40 storeys totaling 3,965 units and a linear park
Reference Number: ZBA2024-0002
Property Address: 0 Prince William Boulevard; 1800 and 1850 Bowmanville Avenue
Municipality/UT: Clarington/Durham
OLT Case No: OLT-24-001024
OLT Lead Case No: OLT-24-001025
PROCEEDING COMMENCED UNDER section 51(34) of the Planning Act, R.S.O. 1990, c. P. 13, as amended.
Applicant/Appellant: 668390 Ontario Ltd. and 829426 Ontario Inc.
Subject: Proposed Plan of Subdivision – Failure of Approval Authority to make a decision
Description: To permit a mixed-use building consisting of nine high-rise buildings up to 40 storeys totaling 3,965 units and a linear park
Reference Number: S-C-2024-0001
Property Address: 0 Prince William Boulevard; 1800 and 1850 Bowmanville Avenue
Municipality/UT: Clarington/Durham
OLT Case No: OLT-24-001023
OLT Lead Case No: OLT-24-001025
BEFORE:
STEVEN COOKE
VICE-CHAIR
Friday, the 30th day of January, 2026
THIS MATTER having come before the Tribunal for a Case Management Conference and with the Tribunal’s Decision and the Procedural Order issued March 25, 2025;
AND THE TRIBUNAL having received a request on consent of the Parties to amend the dates contained in the Procedural Order;
THE TRIBUNAL ORDERS that the dates from the Procedural Order are amended in the chart of key dates as follows:
| Date | Hearing Event |
|---|---|
| February 13, 2026 | Delivery of Applicant’s Urban Design Witness Statement |
| March 6, 2026 | Exchange of Reply Witness Statements |
| March 23, 2026 | Exchange of Visual Evidence |
| March 30, 2026 | Filing of Joint Document Book |
| April 10, 2026 | Filing of Hearing Plan |
| May 13, 2026 | Confirmation to Tribunal if all reserved hearing dates are still required |
| July 13, 2026 | Hearing Commences |
“Matthew D.J. Bryan”
MATTHEW D.J. BRYAN
REGISTRAR
Ontario Land Tribunal
Website: olt.gov.on.ca Telephone: 416-212-6349 Toll Free: 1-866-448-2248
The Conservation Review Board, the Environmental Review Tribunal, the Local Planning Appeal Tribunal and the Mining and Lands Tribunal are amalgamated and continued as the Ontario Land Tribunal (“Tribunal”). Any reference to the preceding tribunals or the former Ontario Municipal Board is deemed to be a reference to the Tribunal.