Ontario Land Tribunal
Tribunal ontarien de l’aménagement du territoire
ISSUE DATE: September 3, 2025 CASE NO(s).: OLT-22-002301
PROCEEDING COMMENCED UNDER subsection 34(11) of the Planning Act, R.S.O. 1990, c. P. 13, as amended
Applicant and Appellant: Huntingwood Trails (Collingwood) Ltd.
Subject: Application to amend Zoning By-law No. 2010-040 – Refusal or neglect of Town of Collingwood to make a decision
Existing Zoning: Rural, Environmental Protection
Proposed Zoning: Residential R2, Residential R3, Environmental Protection, Recreational, Commercial
Purpose: To permit a 170-unit subdivision development
Property Address/Description: Part of Lots 47, 48 and 49, Concession 12
Municipality: Town of Collingwood
Municipal File No.: D14211
OLT Case No.: OLT-22-002301
OLT Lead Case No. OLT-22-002301
OLT Case Name: Huntingwood Trails (Collingwood) Ltd v. Collingwood (Town)
PROCEEDING COMMENCED UNDER subsection 51(34) of the Planning Act, R.S.O. 1990, c. P. 13, as amended
Applicant and Appellant: Huntingwood Trails (Collingwood) Ltd.
Subject: Proposed Plan of Subdivision - Failure of Town of Collingwood to make a decision
Purpose: To permit a 170-unit subdivision development
Property Address/Description: Part of Lots 47, 48 and 49, Concession 12
Municipality: Town of Collingwood
Municipal File No.: D1201111
OLT Case No.: OLT-22-002311
OLT Lead Case No. OLT-22-002301
INTERIM ORDER
B E F O R E:
"T.F. Ng" MEMBER
Wednesday the 3rd day of September, 2025
WHEREAS THE TRIBUNAL having issued its Decision in OLT-22-002301 on September 19, 2022, following a settlement hearing, amended Zoning By-law 2010-040 and approved the Draft Plan of Subdivision #D1201111 (the "Draft Plan") subject to the fulfillment of conditions, including a condition that approval of the Draft Plan is for a period of three years (the "Lapsing Condition");
AND THE TRIBUNAL having been informed that because of the Lapsing Condition, the Draft Plan is scheduled to lapse on September 19, 2025;
AND THE TRIBUNAL having received a Notice of Appeal of the Lapsing Condition pursuant to subsection 51(43) of the Planning Act, seeking an extension of the Lapsing Condition to September 19, 2028;
AND THE TRIBUNAL having been informed that the Town of Collingwood's Director of Growth and Development authorized the extension of the lapsing period to October 19, 2025;
THE TRIBUNAL ORDERS that approval of the Draft Plan is extended on an interim basis and shall lapse on October 19, 2025;
AND THE TRIBUNAL FURTHER ORDERS that a one-hour Telephone Conference (TCC) take place on October 15, 2025 in relation to this matter;
AND THE TRIBUNAL FURTHER ORDERS that it may be spoken to in the event any matter or matters should arise in the connection with the implementation of this Interim Order.
"Matthew D.J. Bryan"
MATTHEW D.J. BRYAN REGISTRAR
Ontario Land Tribunal Website: olt.gov.on.ca Telephone: 416-212-6349 Toll Free: 1-866-448-2248
The Conservation Review Board, the Environmental Review Tribunal, the Local Planning Appeal Tribunal and the Mining and Lands Tribunal are amalgamated and continued as the Ontario Land Tribunal ("Tribunal"). Any reference to the preceding tribunals or the former Ontario Municipal Board is deemed to be a reference to the Tribunal.