Ontario Land Tribunal
Tribunal ontarien de l’aménagement du territoire
ISSUE DATE: August 20, 2025
CASE NO.:
OLT-24-001152
OLT-24-001153
OLT-24-001154
PROCEEDING COMMENCED UNDER subsection 22(7) of the Planning Act, R.S.O. 1990, c. P.13, as amended
Applicant and Appellant: Newdev Investments Ltd. & 1375920 Ontario Limited
Subject: Request to amend the Official Plan – Failure to adopt the requested amendment
Description: to construct two 3-storey back-to-back stacked townhouse blocks
Reference Number: OPA/ZBA 18 139486
Property Address: 5305 & 5307 Highway 7 East
Municipality/UT: City of Markham
OLT Case No.: OLT-24-001153
OLT Lead Case No.: OLT-24-001153
OLT Case Name: Newdev Investments Ltd. & 1375920 Ontario Limited v. Markham (City)
PROCEEDING COMMENCED UNDER subsection 34(11) of the Planning Act, R.S.O. 1990, c. P.13, as amended
Applicant and Appellant: Newdev Investments Ltd. & 1375920 Ontario Limited
Subject: Application to amend the Zoning By-law – Refusal or neglect to make a decision
Description: to construct two 3-storey back-to-back stacked townhouse blocks
Reference Number: OPA/ZBA 18 139486
Property Address: 5305 & 5307 Highway 7 East
Municipality/UT: City of Markham
OLT Case No.: OLT-24-001154
OLT Lead Case No.: OLT-24-001153
PROCEEDING COMMENCED UNDER subsection 41(12) of the Planning Act, R.S.O. 1990, c. P.13, as amended
Appellant: Newdev Investments Ltd. & 1375920 Ontario Limited
Subject: Site Plan
Description: to permit stacked townhouses including site specific development standards
Reference Number: SPC 20 139486
Property Address: 5305 & 5307 Highway 7 East
Municipality/UT: City of Markham
OLT Case No.: OLT-24-001152
OLT Lead Case No.: OLT-24-001153
BEFORE: S. TOUSAW VICE-CHAIR
Wednesday, the 20^th^ day of August, 2025
THESE MATTERS having come before the Ontario Land Tribunal (the “Tribunal”) for a Case Management Conference on May 6, 2025;
AND THE TRIBUNAL having issued the Procedural Order on May 21, 2025, for the purpose of governing the required procedures leading up to the hearing commencing on October 6, 2025;
AND THE TRIBUNAL having received a request, on consent of the Parties, to amend some of the procedural timelines contained in the Procedural Order;
THE TRIBUNAL ORDERS that the following dates from the Procedural Order are amended:
Witness List – from July 31 to August 25, 2025;
Witness Statement – from August 26 to September 12, 2025;
Reply Witness Statement – from September 11 to September 19, 2025.
In all other respects the Procedural Order remains the same.
“Matthew D.J. Bryan”
MATTHEW D.J. BRYAN
REGISTRAR
Ontario Land Tribunal
Website: olt.gov.on.ca Telephone: 416-212-6349 Toll Free: 1-866-448-2248
The Conservation Review Board, the Environmental Review Tribunal, the Local Planning Appeal Tribunal and the Mining and Lands Tribunal are amalgamated and continued as the Ontario Land Tribunal (“Tribunal”). Any reference to the preceding tribunals or the former Ontario Municipal Board is deemed to be a reference to the Tribunal.