ISSUE DATE: April 23, 2025
CASE NO(S).: OLT-24-000793
PROCEEDING COMMENCED UNDER section 14 of the Development Charges Act, 1997, S.O. 1997, c. 27
Appellant: Ontario Greenhouse Vegetable Growers
Description: Determination of the development charges
Reference Number: Bylaw 30-2024- Chatham-Kent Development Charges Bylaw
Property Address: City-wide
Municipality/UT: Chatham-Kent
OLT Case No.: OLT-24-000793
OLT Lead Case No.: OLT-24-000793
OLT Case Name: Ontario Greenhouse Vegetable Growers v. Chatham-Kent (Municipality)
Heard: April 15, 2025 by video hearing
APPEARANCES:
Parties
Counsel
Ontario Greenhouse Vegetable Growers
Steven O’Melia
Municipality of Chatham-Kent
David Taylor
MEMORANDUM OF ORAL DECISION DELIVERED BY M. Quesnel ON April 15, 2025, AND ORDER OF THE TRIBUNAL
INTRODUCTION
1A first Case Management Conference (“CMC”) with respect to an Appeal filed pursuant to s. 14 of the Development Charges Act, 1997 by Ontario Greenhouse Vegetable Growers against the approval by the Municipality of Chatham-Kent (“Municipality”) of Development Charges (“DCs”) By-law No. 30-2024 (“DC By-law”), being a new Development Charges By-law for the Municipality, was held on November 28, 2024.
2At that time the Parties requested a second CMC to be held later to permit them to continue settlement discussions. The Parties were directed to submit a draft Procedural Order (“DPO”) or Issues List (“IL”) or to advise the Tribunal by April 8, 2025, if they wanted to convert the second CMC to a Settlement Hearing. Nothing was received by that date.
PARTY / PARTICIPANT STATUS REQUESTS
3There were no requests for Party or Participant status either before or during the CMC.
UPDATE / NEXT STEPS
4The Tribunal has not received a DPO or IL as the Parties are currently engaging in settlement discussions. The Parties requested that a third CMC to allow for the settlement discussions to continue and to obtain an expert’s report. The Parties were reminded of the importance of advising the Tribunal in advance if an adjournment is requested or if the next CMC can be converted into a Settlement Hearing. At the Parties mutual request, the Tribunal scheduled a third CMC as provided below.
5With agreement from the Parties, the Tribunal directed them to either request the third CMC be converted to a settlement hearing or submit a DPO and IL to the Case Coordinator by Thursday, July 10, 2025, for finalization and approval at the third CMC.
HEARING EVENT
6The Tribunal scheduled a third CMC for Friday, July 18, 2025, at 10 a.m. by Video Hearing.
7Parties are asked to log in to the event at least 15 minutes before it begins to test their video and audio connections:
GoTo Meeting: https://global.gotomeeting.com/join/687587165
Access code: 687-587-165
8Parties are asked to access and set up the application well in advance of the event to avoid unnecessary delay. The desktop application can be downloaded at GoTo Meeting or a web application is available at: https://app.gotomeeting.com/home.html
9Persons who experience technical difficulties accessing the GoToMeeting application or who only wish to listen to the event can connect to the event by calling in to the audio-only telephone line: +1 (647) 497-9373 or (Toll-Free) 1-888-299-1889. The access code is as indicated above.
10Individuals are directed to connect to the event on the assigned date at the correct time. It is the responsibility of the persons participating in the event to ensure that they are properly connected at the correct time. Questions prior to the event may be directed to the Tribunal’s Case Coordinator.
MEDIATION
11The Tribunal advised the Parties of the option of Tribunal-led mediation and to contact the Case Coordinator to determine next steps if the need for mediation arises.
ORDER
12THE TRIBUNAL ORDERS that:
a) A third Case Management Conference will be held by Video Hearing as scheduled above; and
b) The Parties are to either request the third Case Management Conference be converted to a settlement hearing or submit the final draft Procedural Order with the final Issues List to the Tribunal for finalization and approval at the third Case Management Conference, as directed above.
13No further notice is required.
14The Member is not seized of this matter.
“Mathieu Quesnel”
Mathieu Quesnel
MEMBER
Ontario Land Tribunal
Website: www.olt.gov.on.ca Telephone: 416-212-6349 Toll Free: 1-866-448-2248
The Conservation Review Board, the Environmental Review Tribunal, the Local Planning Appeal Tribunal and the Mining and Lands Tribunal are amalgamated and continued as the Ontario Land Tribunal (“Tribunal”). Any reference to the preceding tribunals or the former Ontario Municipal Board is deemed to be a reference to the Tribunal.