Ontario Land Tribunal
Tribunal ontarien de l’aménagement du territoire
ISSUE DATE: November 24, 2025
CASE NO(S).: OLT-24-001019
PROCEEDING COMMENCED UNDER subsection 53(19) of the Planning Act, R.S.O. 1990, c. P. 13, as amended.
Applicant/Appellant: Domenico Pisani
Subject: Severance - refused by Approval Authority
Description: To facilitate the severance of a new residential lot and to accommodate the existing single-detached dwelling and a proposed single-detached dwelling on the resulting two lots.
Reference Number: CN-24-07
Property Address: 76 Bond Crescent
Municipality/UT: Richmond Hill/York
OLT Case No: OLT-24-001019
OLT Lead Case No: OLT-24-001019
OLT Case Name: Pisani v Richmond Hill (City)
PROCEEDING COMMENCED UNDER section 45(12) of the Planning Act, R.S.O. 1990, c. P. 13, as amended.
Applicant/Appellant: Domenico Pisani
Subject: Minor Variance - refused by Approval Authority
Description: To facilitate the severance of a new residential lot and to accommodate the existing single-detached dwelling and a proposed single-detached dwelling on the resulting two lots.
Reference Number: MV-24-41
Property Address: 76 Bond Crescent
Municipality/UT: Richmond Hill/York
OLT Case No: OLT-24-001020
OLT Lead Case No: OLT-24-001019
Heard: November 30, 2024, February 10, 2025 by Video Hearing
APPEARANCES:
Parties
Counsel
2793877 Ontario Limited (“Applicant”)
Riccardo Di