Ontario Land Tribunal
Tribunal ontarien de l’aménagement
du territoire
ISSUE DATE:
February 16, 2024
CASE NO.:
OLT-23-000747
PROCEEDING COMMENCED UNDER section 34(11) of the Planning Act, R.S.O. 1990, c. P. 13, as amended.
Applicant/Appellant: Fouro Towers Builders Ltd. & Sasson Construction Inc.
Subject: Application to amend the Zoning By-law – neglect to make a
decision
Description: Proposed two high rise mixed-used towers
Reference Number: ZA 18 140091
Property Address: 9331-9399 Markham Road
Municipality/UT: Markham/York
OLT Case No: OLT-23-000747
OLT Lead Case No: OLT-23-000747
PROCEEDING COMMENCED UNDER section 41(12) of the Planning Act, R.S.O. 1990, c. P. 13, as amended.
Applicant/Appellant: Fouro Towers Builders Ltd. & Sasson Construction Inc.
Subject: Site Plan
Description: Proposed two high rise mixed-used towers
Reference Number: 22.114181.000.00.SPC
Property Address: 9331-9399 Markham Road
Municipality/UT: Markham/York
OLT Case No: OLT-23-000748
OLT Lead Case No: OLT-23-000747
BEFORE:
C. HARDY
Friday, the 16th
MEMBER
day of February, 2024
THE TRIBUNAL ORDERS that further to the Decision issued on November 22, 2023 and the amended Procedural Order issued on January 29, 2024, the Procedural Order, as agreed to between the Parties and attached hereto as Schedule “A”, shall be in force and effect for the purpose of governing the required procedures leading up to and including the hearing, which is scheduled to commence on April 15, 2024. The Tribunal has set aside 10 days for the hearing.
“Euken Lui”
EUKEN LUI
ACTING REGISTRAR
Ontario Land Tribunal
Website: olt.gov.on.ca Telephone: 416-212-6349 Toll Free: 1-866-448-2248
The Conservation Review Board, the Environmental Review Tribunal, the Local Planning Appeal Tribunal and the Mining and Lands Tribunal are amalgamated and continued as the Ontario Land Tribunal (“Tribunal”). Any reference to the preceding tribunals or the former Ontario Municipal Board is deemed to be a reference to the Tribunal.
Schedule A