The appellant hired the respondents to construct a basement apartment.
The respondents abandoned the project, forcing the appellant to hire another contractor to complete the work.
The appellant sued in Small Claims Court and was awarded damages, but appealed the assessment.
The Divisional Court dismissed most grounds of appeal, finding no palpable and overriding error in the trial judge's factual findings.
However, the court found errors of law in the trial judge's denial of additional financing costs and prejudgment interest.
The appeal was allowed in part, increasing the damages award and granting prejudgment interest.