The defendant contractor brought a motion for summary judgment alleging the plaintiff subcontractor repudiated a contract for the supply and installation of structural steel on a retail construction project.
The plaintiff asserted the defendant wrongfully terminated the contract and claimed payment under a construction lien.
The court found numerous genuine issues requiring a trial, including whether either party fundamentally breached or repudiated the contract, whether time was of the essence where no delivery date appeared in the subcontract, whether consultant review of shop drawings was required before fabrication drawings were produced, and whether delays were attributable to the contractor or consultants.
The court also held that issues concerning the timeliness and quantum of the construction lien, damages, mitigation, and credibility disputes could not be fairly determined on a summary judgment motion.