The plaintiff drywall contractor brought a motion for summary judgment against the defendant general contractor for the balance owing on a construction contract and for over $1.1 million in alleged extras.
The defendant admitted a portion of the contract balance and a portion of the extras but disputed the remainder, citing delays, deficiencies, and lack of written authorization for the extras.
The court granted partial summary judgment for the $750,641 admitted by the defendant but dismissed the balance of the motion, finding that the conflicting evidence regarding verbal authorizations, design changes, and project delays required a trial.