Status hearing motion granted; plaintiff showed acceptable explanation for delay and no non-compensable prejudice.
The plaintiff moved for a status hearing under Rule 48.14(5) to extend the set down deadline in an action regarding alleged construction defects in a custom home.
Only one defendant opposed the motion.
The Master found that the plaintiff provided an acceptable explanation for the litigation delay, noting that much of it was due to accommodating the defendants' requests.
The Master also found no evidence of non-compensable prejudice to the defendants.
The motion was granted, and a timetable was set for the remaining interlocutory steps.
Maier v. Cedarbuilt Project Management Ltd., 2021 ONSC 2894