Schindler Elevator Corporation brought an action to perfect a construction lien for unpaid services and materials supplied for the installation of elevators at the Women's College Hospital redevelopment project.
The general contractor, Walsh Construction/Bondfield Partnership (WBP), counterclaimed for delay impact losses, liquidated damages, and indemnification for penalties, alleging Schindler's delayed performance critically impacted the project schedule.
The court found that while Schindler breached the subcontract by delayed performance, WBP failed to prove that Schindler's delays impacted the critical path of the project or caused the majority of the claimed damages.
Schindler was awarded judgment for the unpaid subcontract balance, less minor set-offs for direct impacts, and WBP's claims against Schindler and its surety, Zurich, were dismissed.