The plaintiff contractor sued the defendant municipality for unpaid amounts under a unit-price contract for road reconstruction.
The claims included unpaid quantities of unit-price line items, unpaid claims for changes or extra work asserted during the project, and claims for changes and extras discovered during litigation.
The court first determined that the claims discovered during litigation were barred due to failure to provide timely notice, but the municipality had waived strict compliance with notice provisions for claims asserted during the project.
The court then analyzed each of the 36 individual claims, weighing the evidence of the parties' respective witnesses and records.
Ultimately, the court awarded the plaintiff $547,261.75 plus pre-judgment interest.