An electrical subcontractor brought a construction lien action seeking payment for overtime and premium labour charges and other alleged extras arising from work performed during the construction of an automotive assembly plant.
The subcontract was a stipulated price agreement under the CCA1 standard form, requiring written notice of claims for adjustments to the subcontract price.
The court held that labour performed during premium shifts was within the scope of the subcontracted work and did not constitute “extra work.” The subcontractor also failed to comply with the contractual notice provisions, which operated as a condition precedent to recovery.
Most additional claims were dismissed for the same reason, although the defendant’s counterclaim for a back charge was also dismissed because the evidence did not establish that the subcontractor’s scope included the high-voltage work in question.