Following an interpleader application regarding funds held for a construction project, two creditors asserted priority claims which were dismissed.
Two other respondents took the lead in opposing these priority claims and subsequently sought their costs.
The court awarded $10,000 in partial indemnity costs to the successful respondents, to be paid equally by the unsuccessful creditors, with the award divided 60/40 in favour of the respondent who took the primary lead.