The plaintiff contractor registered a construction lien and claimed payment for services and materials supplied to build a commercial addition for the defendant owner.
The project was delayed primarily due to issues relocating a hydro transformer, leading the owner to terminate the contract and claim set-off for completion costs and deficiencies.
The court found mutual breaches of contract but determined the owner owed the contractor $146,735.50 for unpaid certified work, subject to allowable backcharges of $54,917.95.
The court awarded the contractor the net balance of $91,817.55 plus prejudgment interest, while dismissing several of the owner's backcharge claims for lack of proof or failure to plead them.