The appellant appealed the Director's decision to issue a Renewable Energy Approval for a 9-turbine wind facility on the Oak Ridges Moraine.
The appellant argued the project would cause serious harm to human health due to noise, shadow flicker, and safety risks, and serious and irreversible harm to the natural environment, including groundwater and bird species at risk.
The Tribunal found the appellant failed to meet its onus of proving the statutory tests under the Environmental Protection Act, relying on the expert evidence provided by the approval holder.
The appeal was dismissed and the Director's decision confirmed.