The appellant owner appealed a summary judgment finding it liable to pay a subcontractor directly for amounts owed by the contractor, pursuant to a termination agreement.
The Divisional Court dismissed the appeal on the merits, finding the motion judge made no palpable and overriding error in concluding the owner agreed to pay the subcontractor's outstanding balance.
However, the court set aside the motion judge's award of 24% interest, finding the issue was not properly addressed, and directed the parties to provide further written submissions on the proper calculation of interest.